Out of interest and i know it was the 60s so different standards and passenger volumes, how was the rebuild managed then ?
The station rebuild in the mid 60s was done largely concurrent with electrification. Although in the main the track layout was not significantly altered. It was done by diverting most of the traffic away - Birmingham trains to Paddington, Manchester trains and some Scotland passengers to St Pancras, postal traffic to a temporary facility on the south / west side of the tracks near Kilburn High Road (there’s still a Royal Mail facility there now). Commuting numbers on what is now the LNR services were much less than today. Took a few years.
For the remodelling 1999-2000, the staton itself was largely untouched (except for making the ramp down to 16-18 much wider), but all the tracks, signalling and OLE (but not all the gantries) were replaced. There was a year and a half of prep works and some of the less disruptive stuff, mostly involving weekend / overnight works where some of the tracks were worked on, but the station remained open. Then from Easter to October 2000 there was a temporary timetable with reduced service levels and roughly one third of the station taken out of use at a time. From memory 15-18 were taken out for the first few weeks, then 12-18, then 8-14, and finally 1-7.
The service reductions took out a handful of peak Virgin services, about 30% of the Silverlink peak (partly offset with 12 coach trains where possible) and the DC (overgrounds) were diverted to the NLL for the duration. Sleepers were a bit tricky as there was only one platform for them throughout, so they had to follow each other in; if the first arrival was late the second had to be held in Wembley or Kensal Green Loop until the platfrom was free. Of course this was in the days when there were fewer services - the standard off peak pattern was 5/6 Virgins, 5 Silverlinks, and 3 DC services (Silverlink Metro). Essentially the timetable was 12 trains per hour max, keeping a path clear in the off peak and squeezing another path in during the peak. It also helped that back then the morning Silverlink peak was done by 0900, whereas the Virgin peak was 0900-1000.
It all worked pretty well, except for the contractor cutting through the air main to the points on day one. Also Hatfield happened about a week after the main blockade finished, so it was a while until passengers felt the benefit of the new layout as temproary timetables were in force.
I’ve found this thread fascinating. Clearly Euston needs rebuilding, and it does get crowded, however I have never found it to be unsafe. I use it about 4 times a week, generally at peak time.
One thing - plans for the rebuilding of Euston have been under development for some time - a lot of time and effort (and money) has gone into it. The HS2 change of strategy has of course affected the timing and design of the conventional station rebuild. Regardless, it is a massive job and will not be cheap.