• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Levenmouth rail link to reopen: project updates

Status
Not open for further replies.

fgwrich

Established Member
Joined
15 Apr 2009
Messages
9,848
Location
Hampshire
Why is the formation so wide at this point?
Because the original Cameron Bridge station was a large island platform, with a smaller island closer to the Distillery plus associated goods lines. Due to exclusion zone restrictions on the distillery and because of the formation through here, they've decided to build the new staton closer to Leven.

The saddest part of this though is that Diageo still has chosen not to stump up for a rail connection to the site - one of Scotland's largest IIRC.

 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
From the project page on the Scotland's Railway site, video of tracklaying at the new Cameron Bridge station.


Meanwhile, the latest post on the Facebook page linked in #350 shows nearly all the rebar in place for the second abutment at Bawbee bridge.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
All information in this post comes from recent posts on the Facebook page linked in #350.

The abutments of the replacement Bawbee bridge have been completed and their formwork stripped. The reinforced concrete floor under the bridge has been waterproofed.

The edge walls of the island platform for Leven station were already in place on both the landward and seaward sides of the bridge, with a gap under and immediately adjacent to the bridge. I had been wondering whether the next step would be to fill in the gap in the platform walls, or to build the superstructure of the bridge. This question has been answered as edge units for the platform walls have been delivered.

Tracklaying has passed the new Cameron Bridge station site and may get close to Leven within the next week or two. Ballast appears to be in place all the way to Leven.

There is at least one footbridge over the line yet to go in.

Does anyone know for certain whether the issues concerning drainage and flood risk at Leven station have been resolved?
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
The Facebook page linked in #350 is now showing that concrete beams for the replacement span of Bawbee bridge have been delivered, and two cranes have arrived, the smaller one to assemble the larger one which will place the beams.

Also, tracklaying is close to Leven station, but not yet quite so close that the platform has appeared in the same photo as rails or sleepers.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
9,848
Location
Hampshire
The Facebook page linked in #350 is now showing that concrete beams for the replacement span of Bawbee bridge have been delivered, and two cranes have arrived, the smaller one to assemble the larger one which will place the beams.

Also, tracklaying is close to Leven station, but not yet quite so close that the platform has appeared in the same photo as rails or sleepers.

A photo tonight on Facebook from one of the Freightliner drivers shows just how close they are now to tracklaying inside the confines of the station - I’d say they are about 30ft from the eastern line meeting the platform edge, something likely to be achieved by the weekend.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
A photo tonight on Facebook from one of the Freightliner drivers shows just how close they are now to tracklaying inside the confines of the station - I’d say they are about 30ft from the eastern line meeting the platform edge, something likely to be achieved by the weekend.
His photos are now on the Facebook page discussed above. Leven station and the approaching head of rail can be seen, and in one of them the crane placing the beams on the Bawbee bridge. No Facebook login required despite what the link says.




Edit: and here is the first beam being lifted last night:


There seems to be a crescendo of work going on. Do the contractors get extra money for work completed by the end of July? Or is there a budget to be used up by that date?
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
Press release about a visit by Jenny Gilruth, now no longer transport minister but just the local MSP.

As the completion date gets nearer, I wonder if they've noticed that the Notes For Editors still say, as in most press releases for the last year and a half, that the project includes "electrification of the line" rather than "provision for future electrification".


Jenny Gilruth, Member of the Scottish Parliament (MSP) for Mid-Fife and Glenrothes visited the site of Levenmouth Rail Link project to see first-hand the latest progress on the £116m Scottish Government investment.

Work is ongoing across the six-mile rail corridor on the project that will see the Fife town reconnected to the mainline rail network for the first time in more than five decades.

As well as meeting the team delivering the project and getting an overview of the work and progress to date, Ms. Gilruth visited the sites of both Cameron Bridge and Leven stations to see first-hand progress on both developments.

Located southeast of Windygates, just off the A915, Cameron Bridge station will have 125 car parking spaces with provision for electric vehicle charging, accessible spaces and cycle storage.

At Cameron Bridge, significant progress has already been made on the rail-focussed elements of the development, including the platforms, lift-pit and bridge foundations and car-park drainage. Track-laying has also recently passed through the new station.

Construction of Leven station is progressing in tandem with the work to rebuild the Bawbee bridge - which sits above the site of the station. As well as seeing the reconstruction of the new bridge above the railway, the MSP saw first-hand the progress that has been made to create Leven station’s 200m island platform.

Completion of the branch line in Spring 2024 will see trains call at Cameron Bridge and Leven stations for the first time since 1969.



----------------- automerge --------------------


Recent posts on the Facebook page linked in #350 show various works to the Bawbee bridge rail span, culminating in the concrete pour for the deck on 10 Aug; laying ballast on each side of the island platform at Leven; the beginnings of buildings at Cameron Bridge station; and the installation of guard (or perhaps I mean check) rails on the route.

This picture gives a good overview of the Leven station area before the concrete pour:


There are two new NR press releases. Planning permission has been received for Leven station:


Network Rail has secured planning permission for the construction of the new Leven station as part of the £116m Scottish Government-funded Levenmouth Rail Link project.

The station will boast 205m island platforms and a pebble styled pavilion area as the entrance to the new station.

Located next to Leven leisure centre, the station will have easy access to connecting bus services and all existing active travel routes.

It will have 133 car parking spaces with provision for EV charging and cycle storage and there will be ‘blue badge’ accessible parking spaces.

Leven is one of two new stations being built on the new rail link, with the other at Cameron Bridge also now under construction.

A planning application was submitted for the development in October 2022 with the work on building the rail-facing elements of the station getting underway in February 2023. This was enabled by permitted development within the railway corridor.

Since breaking ground in February, engineers have created the new island platforms for the station using 98 pre-cast units and around 200 cubic metres of concrete. This happened in tandem with the redevelopment of the Bawbee Bridge which sits above the station site.

Joe Mulvenna, programme manager for Network Rail said: “Securing planning permission for Leven station is another step in the right direction for the project. It takes us closer to getting the full station development built and opened for public use.

“While there are conditions attached to the planning consent, these come as no surprise to us, and we are busy working through these with Fife Council so we can proceed as planned with the work.

“Every step forward is exciting, but the award of planning consent is a milestone that moves us ever closer to opening the rail link for the people of Fife.”

and a planning application has been submitted for a long new footbridge:


Network Rail has submitted a planning application to Fife Council to build a bridge over the new railway between Kirkland and Mountfleurie.

It will provide a safe crossing point over the new £116m Scottish Government-funded railway, which connects Levenmouth to the rail network for the first time in over 50 years.

The structure has been designed and funded as part of Fife Council’s upgrade and expansion of active travel routes in the area and will maintain the path between Kirkland and Mountfleurie.

Construction will begin on the bridge and supporting path/cycle routes in late autumn and there will be a diversion route will be in place during this time.

It’s anticipated that the completed structure will be complete and open ahead of the opening of the railway in spring 2024.

Network Rail is inviting local residents to an informal community drop-in event where people can speak with the project team and discuss any queries they may have. Maps and 3D images will be available so people can see the current visuals, as per the planning submission.

The event will take place from 3:30pm to 7:30pm on Tuesday 15 August adjacent to the walking route impacted by the closure and on the site of the new bridge. It will be held in a gazebo situated just past Steelworks Brae where the path leads to the current railway crossing.

Martin McKinlay, senior sponsor for Network Rail said: “We’ve been working closely with Fife Council to develop a plan which means people can still cross the railway at this well-used crossing point.

“The proposals come at a time when people locally can see the railway becoming a reality. The track is now in place through this location and is moving closer to the site of the new Leven Station.

“Our attention can now turn to how we enable people to safely cross the railway in the future and the intention is to have this structure in place prior to the railway opening.

“Given that this is such a significant structure, we know that there will be some disruption during its construction as the path will need to close. This is to allow the work to be delivered safely and we will do what we can to minimise any inconvenience.”

Fife Council has secured funding for the development of the Levenmouth active travel network from the UK Government's Levelling Up Fund.

Further support has been received from the Scottish Government via Places for Everyone, an active travel infrastructure programme administered by Sustrans.

This crossing is a key part of the network and it makes sense for the work to be delivered as part of the scope of the wider Rail Link project.

The planning application for the new bridge at Mountfleurie is now live on Fife Council’s webpage and can be viewed on Fife Council’s planning portal ( Application No: 23/02058/FULL) and is open for public comment as per the standard planning process.

...

Fife Council is funding this bridge as part of a significant expansion and enhancement to the active travel network locally. The approach is the same as with the work to the Bawbee bridge with the work to be delivered as part of the scope of the wider Rail Link project.

As the picture shows but the text strangely doesn't mention, the bridge will also cross the track of the Fife Heritage Railway. According to this (other) Facebook page, it's one of several such proposed bridges on the eastern half of the route:


As far as I know, NR is still not proposing any crossings or footbridges nearer the west end, and there is still a local campaign about this.

These two latest press releases don't mention electrification. One of them doesn't even have a Notes for Editors section.
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
James Wemyss (see #352-#354) has posted this comment on the Facebook page linked in #350.

I got my notification on Monday, that after five attempts by the Design Consultants to get acceptance that the new Leven Station's railtrack, pod building and car park may flood on average every two years, The Fife Council Planners have given approval. This confirmation happened at the correct time to allow the Bawbee Bridge concrete deck to be poured.

...

To gain approval the design had to be altered so that the AfA footpath to the Station would be built above flood level to give safe egress from the Platforms and that an evacuation plan would be in place.
It is yet to be seen if SEPA will upset their Paymasters and lodge a stop notice request as part of a challenge to the Decision in the Court of Session as they are against the Station design and its acceptance that the development will flood (the platforms use up the available volume of new built environment that can be lifted clear of predicted maximum flood water height without causing knock on effect so if the Station was elsewhere the
rail lines could have been lifted clear of the predicted flood water level instead).
I submitted an objection as the seaward end of the Platforms would need to be on a curve if the Line were to be extended for Passenger Train use over to Methil, Buckhaven and onwards to rejoin the main line at Dysart due to the amount of land now being zoned for housing between Leven and Kirkcaldy.
To do this as an alteration in the future from the current design would cause much disruption and my estimate of the all in cost was £10million on top of the cost of providing lift access to the Station platform. The other alternative would have been to terminate the Platform on the Sainsbury's side of the Bawbee Bridge and extending the Platform further towards Cameron Bridge to get the required length.

I also suggested that a consideration be given of providing or safeguarding a route for an AfA ramped bridge access to the Station Platform at its Cameron Bridge end from between the Sainburys and Pfaudler sites to serve passengers coming from that direction (getting their McDonald's) without having to walk all the way to the only Station access at the car park. Also gave and /or thoughts on a ramp down of the Iron Brig onto a path built into a wider six foot (similar to those at some Glasgow Suburban Stations) or from a cross river bridge so that there is a second access route into the Station.
In the Planner's Report of Handling (not the Decision Notice) my Objection resulted in the following entries:
'It has been confirmed by Network Rail that the track and platform layout has been designed for a potential future freight route and there would be no requirement to change the shape of the platform to accommodate this. A sketch was provided by Network Rail which demonstrates this.'
In other words, NR have basically quashed any chance of Passenger Train services being extended beyond Leven Station to serve the housing expansion towards Kirkcaldy as the cost of adaptation of the layout being built would make it unviable? This NR sketch has been removed from the Application document list but luckily it is filed in the link location provided in the above paragraph.
The second entry is:
'Consider providing or giving future route provision protection to an Access for All Footbridge between the Sainburys and Pfaudler sites to land between the twin tracks of the railway (known in the railway world as the 'Six Foot') to give a northern end access to the Station. Variations on this concept are a ramp of the Iron Brig and / or an over river connection into any such footbridge and then into the northern end of the Station. It is understood that the provision of this route is being investigated and the proposals would not prejudice a future access route to the south, however this proposal was outwith the scope of this application.'
So at least I've created some ideas there?
 

jadmor

Member
Joined
26 Nov 2013
Messages
101
Any concrete proposals on service pattern yet or is just speculation? Obviously we expect it to be 1tph via Dunfermline and 1tph via Kirkcaldy as extensions/diversions of the current Cowdenbeath/Glenrothes terminators. Will the Circle services ever return in place of being merged into the Perth/Dundee services?
Scotrail reported that their traffic surveys post Covid showed a very weak market for travel between Dunfermline and Kirkcaldy, so probably not. It would be nice to see a return to a faster service to Perth though- and Aberdeen services stopping at Inverkeithing and Kirkcaldy?c
 

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,260
James Wemyss (see #352-#354) has posted this comment on the Facebook page linked in #350.

The line isn't ever going to be extended for passenger use. That freight extension, maybe, but not for passengers.

It's really not the end of the world if the station floods once every two years so long as it's predictable. The alternative is that there's no station here at all.
 

Tayway

Member
Joined
17 May 2021
Messages
196
Location
Scotland
Scotrail reported that their traffic surveys post Covid showed a very weak market for travel between Dunfermline and Kirkcaldy, so probably not. It would be nice to see a return to a faster service to Perth though- and Aberdeen services stopping at Inverkeithing and Kirkcaldy?c
I think you'd only ever see a return for Kirkcaldy and Inverkeithing stops if Edinburgh to Aberdeen was increased to 2tph – ScotRail have already slowed them down by adding in a Cupar stop all day. Hopefully the pre-Covid status quo returns at some point, with the Dundee and Perth services running semi-fast again.
 

jadmor

Member
Joined
26 Nov 2013
Messages
101
Perhaps they should bring back Thornton Junction as an interchange station, with a shuttle bus to Glenrothes. ;)
 

ld0595

Member
Joined
1 Aug 2014
Messages
632
Location
Glasgow
It's really not the end of the world if the station floods once every two years so long as it's predictable. The alternative is that there's no station here at all.
Why on earth would regular flooding of a brand new multi million pound asset be acceptable?! If they're really expecting it to flood every 2 years then I'd be truly gobsmacked.

Our infrastructure already struggles to handle existing extreme weather events as is it is and that's not going to get any better with an increasing frequency and severity of such weather events due to climate change.
 

takno

Established Member
Joined
9 Jul 2016
Messages
6,141
Why on earth would regular flooding of a brand new multi million pound asset be acceptable?! If they're really expecting it to flood every 2 years then I'd be truly gobsmacked.

Our infrastructure already struggles to handle existing extreme weather events as is it is and that's not going to get any better with an increasing frequency and severity of such weather events due to climate change.
One would assume that the increasing frequency and severity of extreme weather is built into the assessment that it will flood every couple of years. It's quite likely that the original modelling for the location had flooding as a rare event, which has now been upgraded to relatively common. You can't build everything on the top of a hill, so the next logical step is to design the infrastructure to cope with the conditions you're building it in.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
32,315
Location
Scotland
Why on earth would regular flooding of a brand new multi million pound asset be acceptable?! If they're really expecting it to flood every 2 years then I'd be truly gobsmacked.
Only if it's not designed to handle the flooding without damage. It's not really that difficult to do - simple things like having all power outlets at least 50cm higher than the expected flood level, using only waterproof materials and ensuring that the there are no areas that will pond water make it pretty easy to ensure that the station is functional as soon as the water recedes.
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
3,287
Location
belfast
Only if it's not designed to handle the flooding without damage. It's not really that difficult to do - simple things like having all power outlets at least 50cm higher than the expected flood level, using only waterproof materials and ensuring that the there are no areas that will pond water make it pretty easy to ensure that the station is functional as soon as the water recedes.
a building designed like that would really only need a clean after a flood, so not a massive issue provided the structure is designed to handle floods
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
32,315
Location
Scotland
I wonder how much time was spent in committees in the early stages of the current project discussing the implications of flooding on this line?
I hope a significant amount, as with any infrastructure project these days they should be spending a considerable amount of time considering the impacts of changing climate norms.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,267
Location
Bristol
I wonder how much time was spent in committees in the early stages of the current project discussing the implications of flooding on this line?
I'd guess a fair amount because the discussion would have involved the cost of trying to prevent the flooding, and whether that would have had any impact on the viability of the scheme. Hard engineering is very expensive to install, and if it doesn't work it's a real bugger to repair everything that wasn't expecting to be flooded and then replace the hard engineering. Whereas if you design a simple station in the expectation of being flooded, as mentioned upthread all you need afterwards is a clean out but hopefully all the services and utilities are ready and waiting. It's not like the trains would be running through the floods anyway.

The bigger worry with flooding will be what state it leaves the track in afterwards.
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
34,069
Location
A typical commuter-belt part of north-west England
I am mindful, flooding-terms wise, of the situation on the Conwy Valley Line at Dolwyddelan in recent years, where inundation occurred in March 2019 and the through line was closed for repairs until July 2019.

Then inundation occurred again in February 2020 and the line was not reopened until September 2020.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,267
Location
Bristol
I am mindful, flooding-terms wise, of the situation on the Conwy Valley Line at Dolwyddelan in recent years, where inundation occurred in March 2019 and the through line was closed for repairs until July 2019.

Then inundation occurred again in February 2020 and the line was not reopened until September 2020.
The washed out parts weren't designed to handle the volumes of floodwater. Since the rebuild in COVID which was designed with those volumes in mind, AIUI there's been no long-term closures.

Similarly, if Levenmouth is designed knowing it will flood and therefore seals/raises anything that needs to be protected, then there's no reason it can't reopen within a day or two of the waters receding.
 

DynamicSpirit

Established Member
Joined
12 Apr 2012
Messages
8,945
Location
SE London
That presumes that they stable trains there overnight, which is far from a given, since they just won't run trains on the line if there's been flooding.

I'm not so sure. Flooding isn't always completely predictable and can happen suddenly. If you want to have zero risk of a train getting caught in a flood, then the only way to achieve that is probably, to stop running any services and move all the trains away whenever the weather forecast shows any risk that flooding might happen. I'm not sure that would be seen as acceptable to passengers, or would make for a reliable railway.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
32,315
Location
Scotland
I'm not so sure. Flooding isn't always completely predictable and can happen suddenly. If you want to have zero risk of a train getting caught in a flood, then the only way to achieve that is probably, to stop running any services and move all the trains away whenever the weather forecast shows any risk that flooding might happen. I'm not sure that would be seen as acceptable to passengers, or would make for a reliable railway.
How is that any different to any other railway, anywhere else in the country though?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,267
Location
Bristol
I'm not so sure. Flooding isn't always completely predictable and can happen suddenly. If you want to have zero risk of a train getting caught in a flood, then the only way to achieve that is probably, to stop running any services and move all the trains away whenever the weather forecast shows any risk that flooding might happen. I'm not sure that would be seen as acceptable to passengers, or would make for a reliable railway.
Proactive Weather monitoring is done all the time by NR and the TOCs already. Contingency plans are regularly put in place for it, including cancelling trains.
 

DynamicSpirit

Established Member
Joined
12 Apr 2012
Messages
8,945
Location
SE London
How is that any different to any other railway, anywhere else in the country though?

Operationally, it may not be different. I guess the point is that, if an existing railway that was built 150+ years ago is prone to flooding, then the sensible solution is probably to live with the unfortunate choice of where the railway was built and to manage that risk. But if you're building a brand new railway and station, then it seems rather more sensible to design the railway as far as practicable so that it won't regularly flood (for example by building it sufficiently elevated).
 
Status
Not open for further replies.

Top