777009 at Crewe. 005 also with it.
Mark

Mark
Yes it was scheduled to run via Orpington but the units are prohibited through the Up Platform at Knockholt so had to wait for a possession to clear so it could run via the permitted route via Bat and Ball.From what I've read elsewhere, it was apparently something to do with "paperwork routing issues"
Video clip of 66730 hauling new Merseyrail units 777005 and 777009 at Betley Road on the WCML, 8 July 2020, here:
Posted elsewhere as the following:Does anyone have info on the rest of the consist please.
Thanks
Posted elsewhere as the following:
8027970226 IWA
777005 EMU
777009 EMU
8027970218 IWA
8027976954 IWA
8047370071 IGB
8027976178 IWB
8027976780 IWA
Got drowned getting this lol
The rain was unkind.
Filmed at Broad Green.
Anyone have info of the wagons please
006 is the next train, no confirmed plan for unit numbers going forward yet but should be odds one week and evens the next. This is due to odds being built in Poland and evens being built in Switzerland
When is 777006 scheduled to come to the UK?006 is the next train, no confirmed plan for unit numbers going forward yet but should be odds one week and evens the next. This is due to odds being built in Poland and evens being built in Switzerland
006 is a week Thursday so 23rd. And yes should be able to spot them at Kirkdale. Future unit's maybe stored near Southport due to space restrictions at Kirkdale. 003 should be heading to Crew for modifications so it's at the same specification level as 005 and 009 which will reduce the units by one for a while
Which is why I don't understand why they demolised the cleaning shed and never rebuilt more sheds for stabling the new trains at Kirkdale depot. Southport sidings seems to be prone site for graffiti attacks of the current units. There is a spate of attacks going around at the moment.There is no space at Birkenhead for more than one 777. There is still no plan for the rest of the units, but the talk is Butchers sidings which is the non electrified sidings at Sth prt. The network can't take more than 68 units I think, and currently there are 64. 508134 when it leave the network will give on emote space . The problem is storing them safely from being graffitied
What about the shed at Birkenhead Central.There is no space at Birkenhead for more than one 777. There is still no plan for the rest of the units, but the talk is Butchers sidings which is the non electrified sidings at Sth prt. The network can't take more than 68 units I think, and currently there are 64. 508134 when it leave the network will give on emote space . The problem is storing them safely from being graffitied
What about the shed at Birkenhead Central.
Mark
There is no space at Birkenhead for more than one 777. There is still no plan for the rest of the units, but the talk is Butchers sidings which is the non electrified sidings at Sth prt. The network can't take more than 68 units I think, and currently there are 64. 508134 when it leave the network will give on emote space . The problem is storing them safely from being graffitied
That's an old report but were not these problems foreseen when the trains were ordered? The platforms, as the article says, have been raised but nobody mentioned the signalling problem at the time (or didn't tell us the public). Anybody would think the present Government were directly responsible.There was talk last year of them having to possibly set up a base at Southport for storage and maintenance of a small number (14?) of class 507/508 units they will have to retain for longer than originally predicted (possibly until 2022) on the Southport-Hunts Cross line until the work was undertaken to modify the platform lengths and signals due to issues caused when the 777s are used in an 8 car formation.
![]()
Operational problems could delay roll-out of new Merseyrail train fleet | TheBusinessDesk.com
Length of new trains affects signalling at some stations on rush hour services Length of new trains affects signalling at some stations on rush hour serviceswww.thebusinessdesk.com
Anyone heard any further update on when these works to platform lengthening and signal moves may take place?