It's normally easy to spot a project that is running into trouble (GW electrification) by the way the project team and their supporters start to micro-divide the various reporting points so they have at least something to say. It's even got into various threads here.
For example, 50 years ago it was just number of miles completed. More recently it was getting reduced to masts erected, miles wired, etc, but now I notice the GW project getting reported as numbers of mast holes drilled, piles installed, etc, even before there is any sign of things above ground. I suppose the next stage will be to start reporting the number of cubic metres of concrete ordered from Hanson as "progress" ....