Little photo update from myself around Market Harborough's underbridges after meeting @PJM & @Flying Phil on Monday.
South of Scotland Rd (U/B 31), there is a pair of piles - 1 on the DM (not pictured), the other on the UM (pictured).

Northwards, there are 3 on the UM (the 3rd of which is a concrete base), and 5 on the DM (3rd through 5th are concrete).
UM (3 no.):



DM (5 no.):




Meanwhile, north of Kettering Rd (U/B 30):
First structure after the underbridge, confirmed by sight as SPC3/133.097/UM.

Then 3 piles, all on the UM side.



Finally, an unidentified TTC on the UM side before U/B 29 (A4304 Rockingham Rd).

Update on works for April:
Sat/Sun 26/27 March: 2 of 4 lines closed between St Pancras & Luton on Sat eve & all day Sun. 3 EMR tph on MML after 12pm Sunday; Corby reduced to shuttle. (KO1a work assumed)
Sat/Sun 2/3 April: 2 of 4 lines closed between St Pancras & Luton on Sat eve & all day Sun. 3 EMR tph on MML; Corby reduced to shuttle. (KO1a work assumed)
Midweek nights Mon 4 to Sat 9 April: 2 of 4 lines closed between St Pancras & Luton. (KO1a work assumed)
Sat/Sun 9/10 April: Various works that are hard to pin down, but might involve KO1a work
Midweek nights Mon 11 to Fri 15 April (Good Friday): MML closed between Kettering & Market Harborough. This might be some more masts/piles going in!
South of Scotland Rd (U/B 31), there is a pair of piles - 1 on the DM (not pictured), the other on the UM (pictured).

Northwards, there are 3 on the UM (the 3rd of which is a concrete base), and 5 on the DM (3rd through 5th are concrete).
UM (3 no.):



DM (5 no.):




Meanwhile, north of Kettering Rd (U/B 30):
First structure after the underbridge, confirmed by sight as SPC3/133.097/UM.

Then 3 piles, all on the UM side.



Finally, an unidentified TTC on the UM side before U/B 29 (A4304 Rockingham Rd).

Update on works for April:
Sat/Sun 26/27 March: 2 of 4 lines closed between St Pancras & Luton on Sat eve & all day Sun. 3 EMR tph on MML after 12pm Sunday; Corby reduced to shuttle. (KO1a work assumed)
Sat/Sun 2/3 April: 2 of 4 lines closed between St Pancras & Luton on Sat eve & all day Sun. 3 EMR tph on MML; Corby reduced to shuttle. (KO1a work assumed)
Midweek nights Mon 4 to Sat 9 April: 2 of 4 lines closed between St Pancras & Luton. (KO1a work assumed)
Sat/Sun 9/10 April: Various works that are hard to pin down, but might involve KO1a work
Midweek nights Mon 11 to Fri 15 April (Good Friday): MML closed between Kettering & Market Harborough. This might be some more masts/piles going in!