Western Sunset
Established Member
Just wondering how far north on the MML has electrification now been authorised to?
Though the Kegworth 400kV connection has always been needed for HS2, or course, whatever happens to the MML. And there are lots of stages to something being "authorised".a Grid connection has been applied for at Kegworth
However that part of HS2 isn't currently authorised - it would need a Hybrid Bill through Parliament and it's nowhere near that.Though the Kegworth 400kV connection has always been needed for HS2, or course, whatever happens to the MML. And there are lots of stages to something being "authorised".
You have to apply for connections years in advance to get equipment and outages on the EHV system to make the connections. Although if they are connecting at ratcliffe power station grid it should be easier to get outages on a switchboard connection rather than teeing off a pylon route which means taking a complete circuit out of use for several weeks.Though the Kegworth 400kV connection has always been needed for HS2, or course, whatever happens to the MML. And there are lots of stages to something being "authorised".
I understand they are going to tee off one of the 400kV lines, a couple of pylons away from the power station grid. It makes sense, I suppose: you've got to get the 400kV supply over the fence somehow, and using the existing line to do that would be cheaper.if they are connecting at ratcliffe power station grid it should be easier to get outages on a switchboard connection rather than teeing off a pylon route
Thats bizarre far better to have the supply off a switchyard as in the unfortunate case you get a fault on the 400kv traction transformer you don't have to trip off the circuit to clear the fault. Not much choice at Baybrooke and majority of other locations as the infeed isn't near a switchyard.I understand they are going to tee off one of the 400kV lines, a couple of pylons away from the power station grid. It makes sense, I suppose: you've got to get the 400kV supply over the fence somehow, and using the existing line to do that would be cheaper.
You'd hope the Leicester wiring will have passive provision for the long-anticipated capacity scheme there - ie no masts where new tracks would go.The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
If they're not waiting for the final design of the new layout, they may not know where to avoid (other than by having end-to-end gantries everywhere).You'd hope the Leicester wiring will have passive provision for the long-anticipated capacity scheme there - ie no masts where new tracks would go.
Bull. Govt has been announcing loads since the pre-election period started, on a range of things (some transport related, and gaining coverage for it). Either it is happening, or MR is fishing.My copy of the May issue of Modern Railways has arrived. There's an MML item on page 12.
The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.
Pardon my ignorance and possibly silly question - is that Syston South Jct or Syston North Jct please?The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
Not stated but I would guess north, so as to gather all the complexities of the Leicester area into one section.Pardon my ignorance and possibly sill question - is that Syston South Jct or Syston North Jct please?
No local elections in Rwanda this May AFAIK.Bull. Govt has been announcing loads since the pre-election period started, on a range of things (some transport related, and gaining coverage for it). Either it is happening, or MR is fishing.
Syston South to North remained as four tracks in the 1988 remodelling that reduced it to three tracks into Leicester. So the extra track ends at the South junction but there may be some implications further north. This probably explains the rather vague northren limit.Pardon my ignorance and possibly sill question - is that Syston South Jct or Syston North Jct please?
I'm sure the OHLE design team could make a good guess as to where any additional tracks between Syston and Wigston would have to go, and then at least try to avoid planting piles in those locations.If they're not waiting for the final design of the new layout, they may not know where to avoid
This is far from guaranteed.Especially if any new layout in the area is to be at-grade.
I hope someone at NR is looking at Wigston South Junction to Proof House Junction.My copy of the May issue of Modern Railways has arrived. There's an MML item on page 12.
The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.
The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
Yeah but Arley Tunnel...I hope someone at NR is looking at Wigston South Junction to Proof House Junction.
We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?I hope someone at NR is looking at Wigston South Junction to Proof House Junction.
Very true, but the need to grade-separate Wigston North / Syston South is looking less and less likely, given the IRP proposal to build the HS2 Eastern stump to EMD.This is far from guaranteed
This would be consistent with the internal vs external comms about Kettering-MH. There was initial coverage about this back in Feb/Mar 2019 (which might be analogous to the MML commitment in the IRP), but formal announcement that work was underway was only at the end of 2021, by which time quite a lot of work on piling and at Braybrooke had already been done. If the same approach is taken this time, we'll probably see piling North of the current scheme before there's any PR.The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.
We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?
The Network Rail "Leicester Area Strategic Advice" document that basically pours cold water on the need for grade separation is linked here:Very true, but the need to grade-separate Wigston North / Syston South is looking less and less likely, given the IRP proposal to build the HS2 Eastern stump to EMD.
Not necessarily. Wiring Wigston-Proof House instantly allows the Birmingham - Leicester passenger service to switch to EMUs releasing class 170s for cascade. If EMUs could have batteries to cope with Syston-Peterborough-Ely. then more 170s could be cascaded off the Stansted Airport route. .We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?
That sounds remarkably speedy, and quite impressive. Nice to hear some good news on the electrification programmeView attachment 113559View attachment 113560View attachment 113561View attachment 113562View attachment 113563View attachment 113564View attachment 113565
(Via LinkedIn) Braybrooke FS' building has now been lifted into position. The post author, who works for Network Rail, has also implied that the OLE will continue to Wigston in one job lot, and that energisation of the route will be in December 2023, with an entry into service of 2024 as things stand.
This timescale seems fairly reasonable given that Market Harborough northwards is only at the design survey stage, and that the bridge works from Kettering to Mkt H'boro' haven't started yet...