• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

MML Electrification: progress updates

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,375
Location
Dalton GA USA & Preston Lancs
Well - published upthread from extremely reliable sources that a Grid connection has been applied for at Kegworth. So that is huge. With a GF, there would be wires. With wires there would be SPS and bases and masts etc.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,700
Location
Nottingham
Though the Kegworth 400kV connection has always been needed for HS2, or course, whatever happens to the MML. And there are lots of stages to something being "authorised".
However that part of HS2 isn't currently authorised - it would need a Hybrid Bill through Parliament and it's nowhere near that.
 

Nicholas Lewis

On Moderation
Joined
9 Aug 2019
Messages
7,265
Location
Surrey
Though the Kegworth 400kV connection has always been needed for HS2, or course, whatever happens to the MML. And there are lots of stages to something being "authorised".
You have to apply for connections years in advance to get equipment and outages on the EHV system to make the connections. Although if they are connecting at ratcliffe power station grid it should be easier to get outages on a switchboard connection rather than teeing off a pylon route which means taking a complete circuit out of use for several weeks.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,644
Location
Nottingham
if they are connecting at ratcliffe power station grid it should be easier to get outages on a switchboard connection rather than teeing off a pylon route
I understand they are going to tee off one of the 400kV lines, a couple of pylons away from the power station grid. It makes sense, I suppose: you've got to get the 400kV supply over the fence somehow, and using the existing line to do that would be cheaper.
 

Nicholas Lewis

On Moderation
Joined
9 Aug 2019
Messages
7,265
Location
Surrey
I understand they are going to tee off one of the 400kV lines, a couple of pylons away from the power station grid. It makes sense, I suppose: you've got to get the 400kV supply over the fence somehow, and using the existing line to do that would be cheaper.
Thats bizarre far better to have the supply off a switchyard as in the unfortunate case you get a fault on the 400kv traction transformer you don't have to trip off the circuit to clear the fault. Not much choice at Baybrooke and majority of other locations as the infeed isn't near a switchyard.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,644
Location
Nottingham
I did a bit more digging on this. The Kegworth Autotransformer feeder station for HS2 was planned to be adjacent to M1J24, which is actually 3km from Ratcliffe on Soar power station.

1650308078622.png
(image taken from: https://assets.publishing.service.g..._Ratcliffe-on-Soar_to_Long_Eaton_map_book.pdf )

I can't see what 400kV supply they planned to use. None of the several 400kV lines in the area pass directly over the site. See here (map taken from openinframap).
1650308640283.png

But it's all irrelevant now, as the route of HS2 is likely to be diverted to the other side of Kegworth village in order to join the MML south of East Midlands Parkway.

EDIT: The 400kV tap was indeed the second pylon outside the power station. It looks like they planned to feed the Kegworth ATFS with a +25kV/0/-25kV cable buried along the southern side of the A453 between these two sites.

1650309495727.png
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
My copy of the May issue of Modern Railways has arrived. There's an MML item on page 12.

The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.

The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
 
Last edited:

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,047
Location
Mold, Clwyd
The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
You'd hope the Leicester wiring will have passive provision for the long-anticipated capacity scheme there - ie no masts where new tracks would go.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,170
Location
Bristol
You'd hope the Leicester wiring will have passive provision for the long-anticipated capacity scheme there - ie no masts where new tracks would go.
If they're not waiting for the final design of the new layout, they may not know where to avoid (other than by having end-to-end gantries everywhere).
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
Over the years the most frequent talk of capacity improvements in the area has been of a flyover at Wigston North, but I think the most recent document on the subject only referred to all-at-grade improvements (which would not remove conflicts between MML and F2N).
 
Last edited:

londonmidland

Established Member
Joined
22 Dec 2009
Messages
2,039
Location
Leicester
I wonder if they’ll just install wide portals everywhere, to avoid any conflict on the ground, for any potential future track layout changes?
 

YorksLad12

Established Member
Joined
5 Feb 2020
Messages
2,220
Location
Leeds
My copy of the May issue of Modern Railways has arrived. There's an MML item on page 12.

The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.
Bull. Govt has been announcing loads since the pre-election period started, on a range of things (some transport related, and gaining coverage for it). Either it is happening, or MR is fishing.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,375
Location
Dalton GA USA & Preston Lancs
The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
Pardon my ignorance and possibly silly question - is that Syston South Jct or Syston North Jct please?
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
Pardon my ignorance and possibly sill question - is that Syston South Jct or Syston North Jct please?
Not stated but I would guess north, so as to gather all the complexities of the Leicester area into one section.

Bull. Govt has been announcing loads since the pre-election period started, on a range of things (some transport related, and gaining coverage for it). Either it is happening, or MR is fishing.
No local elections in Rwanda this May AFAIK.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,700
Location
Nottingham
Pardon my ignorance and possibly sill question - is that Syston South Jct or Syston North Jct please?
Syston South to North remained as four tracks in the 1988 remodelling that reduced it to three tracks into Leicester. So the extra track ends at the South junction but there may be some implications further north. This probably explains the rather vague northren limit.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,644
Location
Nottingham
If they're not waiting for the final design of the new layout, they may not know where to avoid
I'm sure the OHLE design team could make a good guess as to where any additional tracks between Syston and Wigston would have to go, and then at least try to avoid planting piles in those locations.

Especially if any new layout in the area is to be at-grade.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,700
Location
Nottingham
If they are positioned outside any obvious potential trackbed then that probably guarantees that about 90% of them won't need moving whatever layout changes may take place. TTCs on either side are probably better than portals in that respect, because then if one side becomes a flyover ramp the other side is unaffected. And Bletchley shows that OLE can be reconstructed relatively easily for a new flyover.
 

Mordac

Established Member
Joined
5 Mar 2016
Messages
2,362
Location
Birmingham
My copy of the May issue of Modern Railways has arrived. There's an MML item on page 12.

The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.

The next section being developed, known as Section 2, is Wigston South Junction to Syston Junction, so in other words the Leicester area, which is apparently now being taken forward as a standalone electrification scheme, neither integrated with nor waiting for a capacity improvement scheme. "Work is ongoing to obtain approval to go into design for Section 2."
I hope someone at NR is looking at Wigston South Junction to Proof House Junction.
 

John R

Established Member
Joined
1 Jul 2013
Messages
4,566
I hope someone at NR is looking at Wigston South Junction to Proof House Junction.
We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?
 

InTheEastMids

Member
Joined
31 Jan 2016
Messages
973
The magazine "understands" that DfT authorised Market Harborough to Wigston South Junction in late March but local election purdah prevented a public announcement then. The project will be integrated with the already-in-progress Kettering to MH, so the original target of completion to MH in 2023 is no longer guaranteed.
This would be consistent with the internal vs external comms about Kettering-MH. There was initial coverage about this back in Feb/Mar 2019 (which might be analogous to the MML commitment in the IRP), but formal announcement that work was underway was only at the end of 2021, by which time quite a lot of work on piling and at Braybrooke had already been done. If the same approach is taken this time, we'll probably see piling North of the current scheme before there's any PR.

We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?

Agreed - probably needs both Cl93 and bimode XC trains to get any benefits from electrification, I suspect it's well down the list.

Very true, but the need to grade-separate Wigston North / Syston South is looking less and less likely, given the IRP proposal to build the HS2 Eastern stump to EMD.
The Network Rail "Leicester Area Strategic Advice" document that basically pours cold water on the need for grade separation is linked here:
https://www.networkrail.co.uk/wp-content/uploads/2021/02/Leicester-Area-Strategic-Advice-2021.pdf

Obviously grade separation might get back on the agenda if future forecasts were different from the scenarios therein.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
25,056
Location
Bolton
It sounds to me like it will be rather a long time before any work can begin on the 'section 2' from Wigston South Junction anyway.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,718
Location
Between Beeston (Notts) & Bedlington
Screenshot_20220424-215131_LinkedIn.jpgimage_c107164b-5e01-43d8-b5d9-cc709842781a20220424_215139.jpgimage_b73e7ba7-793a-413b-9da4-22979168654c20220424_215140.jpgimage_f5cc33f8-6ecc-48d0-a6b4-0a2f18ca1bdf20220424_215141.jpgimage_cb150454-23f9-4d4d-90e2-278f12dbe06b20220424_215142.jpgimage_4bb57dcf-d33b-42eb-b384-2d05e1dd4b9f20220424_215144.jpgimage_69a0b90c-f56f-4093-adef-b864be04a7be20220424_215145.jpg
(Via LinkedIn) Braybrooke FS' building has now been lifted into position. The post author, who works for Network Rail, has also implied that the OLE will continue to Wigston in one job lot, and that energisation of the route will be in December 2023, with an entry into service of 2024 as things stand.
This timescale seems fairly reasonable given that Market Harborough northwards is only at the design survey stage, and that the bridge works from Kettering to Mkt H'boro' haven't started yet...
 
Last edited:

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
1,943
Location
South Staffordshire
We're doing well to creep forward northwards up the MML in roughly 10 mile incremental steps at the moment, so starting to look beyond the core route feels very optimistic. Besides, until the whole route between Felixstowe and Nuneaton is approved, surely the benefit of Wigston South to Proof House will be much lower than other schemes?
Not necessarily. Wiring Wigston-Proof House instantly allows the Birmingham - Leicester passenger service to switch to EMUs releasing class 170s for cascade. If EMUs could have batteries to cope with Syston-Peterborough-Ely. then more 170s could be cascaded off the Stansted Airport route. .
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
7,557
View attachment 113559View attachment 113560View attachment 113561View attachment 113562View attachment 113563View attachment 113564View attachment 113565
(Via LinkedIn) Braybrooke FS' building has now been lifted into position. The post author, who works for Network Rail, has also implied that the OLE will continue to Wigston in one job lot, and that energisation of the route will be in December 2023, with an entry into service of 2024 as things stand.
This timescale seems fairly reasonable given that Market Harborough northwards is only at the design survey stage, and that the bridge works from Kettering to Mkt H'boro' haven't started yet...
That sounds remarkably speedy, and quite impressive. Nice to hear some good news on the electrification programme
 

cle

Established Member
Joined
17 Nov 2010
Messages
4,640
That is encouraging.

For Leicester, I can see Wigston as four track but not grade separated.

Equally I can't see that the Leicester decision is super complex - basically pick a side for the extra line/platform - and they will be under pressure now to make that call quickly. My vote would be on the Birmingham side as it's more likely for shorter formed services (if the platform is short, per the plans) - OTOH - a Corby-esque EMU to St Pancras would bring great connectivity for the MML stations to the north, and also at EWR/Bedford. But too long so platforming would be different. But maybe it could be an EWR service itself turning at Leicester (shorter, and diesel for now).
 

Top