MML Electrification: progress updates

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Flying Phil

Established Member
Joined
18 Apr 2016
Messages
1,952
Thanks for the updates - I will try to visit the Three Arches bridge tomorrow, there have been no passenger services over this weekend through Market Harborough.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,519
Location
Between Peterborough & Bedlington
Many thanks for the update

59CosG95 what is the fate of three arches bridge? Not in the country at the moment to witness this momentous (also sad occasion).​

Afraid to say I wasn't able to get a decent enough view from the road to the south; Story's have firmly plonked themselves at the entrance to the field. It did look a hive of activity when I was there, however!
 

Flying Phil

Established Member
Joined
18 Apr 2016
Messages
1,952
The Three Arches Bridge has gone! The bricks and spoil has already been removed from the site. The embankments restored and new grass seed has been applied. There is still a discussion about whether a small steel access bridge will go in but at present it is not happening.
I understand there is still a problem finishing one of the Wistow bridges, the other one is complete now. There is still a 1/2 mile catenary/contact wire gap at Braybrooke.
DSC03558.JPG
 

Skymonster

Established Member
Joined
7 Feb 2012
Messages
1,812
Line closures, longer journeys, fewer trains... First it was Beford-Kettering electrification, then Brent Cross station, overhead upgrades south of Bedford, Dore and Totley, overhead installation between Kettering and Market Harborough. Next it’ll be electrification through Leicester onwards towards Nottingham and Sheffield via Derby, which will be worse as there aren’t the diversion routes. Its getting boring now - trying to use the MML on the weekend can frequently be a pain in the posterior, at best. Just run the flippin’ 810s on diesel for goodness sake, that’s why they’ve got power units hung under four of the five carriages!
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,519
Location
Between Peterborough & Bedlington
Line closures, longer journeys, fewer trains... First it was Beford-Kettering electrification, then Brent Cross station, overhead upgrades south of Bedford, Dore and Totley, overhead installation between Kettering and Market Harborough. Next it’ll be electrification through Leicester onwards towards Nottingham and Sheffield via Derby, which will be worse as there aren’t the diversion routes. Its getting boring now - trying to use the MML on the weekend can frequently be a pain in the posterior, at best. Just run the flippin’ 810s on diesel for goodness sake, that’s why they’ve got power units hung under four of the five carriages!
You're lucky that you even have diversionary routes! The South Wales Valleys (by and large), along with Barrhead/East Kilbride, haven't had that luxury.
At least Syston-Trent Jn should be able to make use of the 4-track arrangement, reducing the number of closed lines during most possessions.
You've also got the Erewash to use when the route via Derby's shut.
 

PJM

Member
Joined
20 Aug 2021
Messages
169
Location
Market Harborough
The Three Arches Bridge has gone! The bricks and spoil has already been removed from the site. The embankments restored and new grass seed has been applied. There is still a discussion about whether a small steel access bridge will go in but at present it is not happening.
I understand there is still a problem finishing one of the Wistow bridges, the other one is complete now. There is still a 1/2 mile catenary/contact wire gap at Braybrooke.
View attachment 158420

Farewell old friend! Clear for the last catenary run now. Thanks for the update Phil.
 
Joined
5 Aug 2015
Messages
14
Location
Norfolk
Line closures, longer journeys, fewer trains... First it was Beford-Kettering electrification, then Brent Cross station, overhead upgrades south of Bedford, Dore and Totley, overhead installation between Kettering and Market Harborough. Next it’ll be electrification through Leicester onwards towards Nottingham and Sheffield via Derby, which will be worse as there aren’t the diversion routes. Its getting boring now - trying to use the MML on the weekend can frequently be a pain in the posterior, at best. Just run the flippin’ 810s on diesel for goodness sake, that’s why they’ve got power units hung under four of the five carriages!
You should try using the GEML! Every few years it decides to be closed every weekend for several months - typically in different places each weekend as well. They don't even build anything new (a new station is on the way this time tbf) it's just renewals. At least on MML you can see wires going up and understand what the point of sacrificing your journeys were. Now I think about it, MML is one of the more divertible lines out there once you get north of Kettering. If they really wanted to, you could try sending trains through Ashby-de-la-zouche and Burton in order to call at Leicester and Derby avoiding Syston, Loughborough and the Trent Junctions (unless your going to Nottingham). Granted, there's no plans to do that and there are likely no passenger drivers who know that route. But when it comes to diversions that are actually used: as previously mentioned the Erewash lines are have been used by XC and EMR and also the alternative approach to Sheffield via Woodhouse which is used late at night.
 

QSK19

Member
Joined
29 Dec 2020
Messages
675
Location
Leicestershire
At least on MML you can see wires going up and understand what the point of sacrificing your journeys were. Now I think about it, MML is one of the more divertible lines out there once you get north of Kettering.
Spot on about the useful diversionary capability of the MML, but, in terms of wires going up, it is finally playing catch-up with other mainlines. It has been a political plaything for years - electrification going ahead one minute, paused the next, cancelled the next, bits of it the next, etc.

I’ve always seen the MML as being the poorer relation compared to the ECML and WCML. Granted the journey times on the MML are shorter in general; however that is no excuse to have neglected it for so long. At least we’re now starting to see decent amounts of electrification and hopefully that keeps advancing northwards.
 
Joined
5 Aug 2015
Messages
14
Location
Norfolk
Spot on about the useful diversionary capability of the MML, but, in terms of wires going up, it is finally playing catch-up with other mainlines. It has been a political plaything for years - electrification going ahead one minute, paused the next, cancelled the next, bits of it the next, etc.

I’ve always seen the MML as being the poorer relation compared to the ECML and WCML. Granted the journey times on the MML are shorter in general; however that is no excuse to have neglected it for so long. At least we’re now starting to see decent amounts of electrification and hopefully that keeps advancing northwards.
I know right! It's crazy that successive governments have looked at it and gone... "nah, doesn't justify it, on cost grounds yknow - just no business case for it...". In this way, the Transpennine route and MML are quite similar in the ways that electrification promises came in and successively got scuppered until now. I believe the electrification of the Airedale and Wharfdale lines in the 1990s was meant to go along with the Huddersfield line, but then it was cancelled and new diesel stock was procured instead - reminds me of Grayling cancelling MML and talking about Bimodes and in the end electrification started to deliver faster than the new trains did.

In some ways, the HST was a bit too good at its job and delayed electrification on every line it touched, maybe when they've done the MML some attention can be turned to the XCML - the true runt of the litter. I've heard the measure is above 4 trains per hour or over 100mph line speed and the railway can be ran cheaper/more efficiently with electric trains. But that equation does dip with bimodes.

It is encouraging the amount of electrification work that has gone on in the last 10 years and that real progress is happening on MML and with TRUP even if progress is glacial. These two schemes are some of the few sources of railway hope left after the demise of HS2.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,519
Location
Between Peterborough & Bedlington

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
6,227
Location
Surrey
Run down from Sheffield earlier and Down Rd looks complete apart from the small section mentioned above. Most of the contractor's compounds have been vacated also so the end must be close but do we have a target date yet for energisation.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
7,962
Location
Dalton GA USA & Preston Lancs

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,355
Neil O’Brien, the MP for South Leicestershire [...]
South Leicestershire lies to the west of his constituency, which is Harborough.
[...] do we have a target date yet for energisation.
Energisation is scheduled for July, by the looks of things.

 

LTJ87

Member
Joined
1 Jun 2008
Messages
140
Network Rail has just put out this press release:

Network Rail

A milestone has been reached for the electrification of the Midland Main Line after the final bridge was demolished on the Kettering to Wigston stretch to prepare for new overhead wires to be powered up.

Over the weekend of 18 and 19 May, engineers successfully demolished the Three Arches bridge near Market Harborough to allow for new wires to be installed between Kettering and Wigston.

Along the Kettering to Wigston stretch, there have been 18 bridges which have seen vital upgrade work to prepare for the new wires.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,603
The Three Arches Bridge has gone! The bricks and spoil has already been removed from the site. The embankments restored and new grass seed has been applied. There is still a discussion about whether a small steel access bridge will go in but at present it is not happening.
I’m struggling to work out why a replacement bridge would ever be needed now, given the new direct road access to the site. Was it used as an unofficial local footpath, because there’s no indication on the OS map?

Does the original landowner still have a long term right of access from south of the railway, even if the site on the north side is now owned by the Grid and Network Rail?
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,355
Having watched the timelapse I note it took longer to do the embankment works than to remove the brickwork. The presser says a replacement bridge "will be re-built in the future once the electrification is complete", which suggests they may not be in any particular rush to put one in place.

Meanwhile, another weekend possession through Market Harborough is pencilled in for 27 and 28 July. During the latter there will be no trains at all between Wellingborough and Leicester/Corby, and if I were a betting man that'll be when Braybrooke ATFS is connected.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
1,719
Location
Nottingham
Having watched the timelapse I note it took longer to do the embankment works than to remove the brickwork.
Does anyone know why the two embankments had different treatments? What is the green lumpy material on the far side?

The presser says a replacement bridge "will be re-built in the future once the electrification is complete", which suggests they may not be in any particular rush to put one in place.
If it's just an accommodation bridge, why didn't they just buy out the landowner?
 

LTJ87

Member
Joined
1 Jun 2008
Messages
140
Another release from Network Rail detailing works over June:


On Saturday 1 and Sunday 2 June, new sections of track and switches & crossings, the specialist equipment that trains use to change tracks from one to another, will be installed, as well as upgrades to overhead line equipment near Bedford to allow new trains to operate at 125mph.

New overhead lines will be installed between Kettering and Wigston on Saturday 8 and Sunday 9 June, with further switches & crossings installed near Cricklewood. Overnight overhead line upgrades will be carried out between Luton and Bedford on Sunday 9 as well as Sunday 30 June.

On Sunday 23 June, the second phase of a major resignalling project will be carried out resulting in no train services between London St Pancras and Wellingborough. This project will result in more reliable journeys for passengers and help signallers make better, more efficient decisions for services.

Separately to the Midland Main Line upgrade work, engineers will be laying new track between Leicester and Peterborough on 22-23 and 29-30 June.
 

QSK19

Member
Joined
29 Dec 2020
Messages
675
Location
Leicestershire
Talk of the 810s entering service mid 2025.
I’d wager a bet on full entry into service being 2026 - technical delays and still no agreement on staff training doesn’t bode well. That’s unless any insiders can confirm otherwise on the latter point (providing they can say anything, of course)
 

blueberry11

Member
Joined
19 Aug 2023
Messages
83
Location
Norwich
Since energizing the Kettering to Wigston stretch is coming within the next few months, I presume that once it's done, the 810s will start testing shortly, followed by entering revenue service in early 2025. Is there still one section of wires missing (where the bridge demolition occurred)?
 

PJM

Member
Joined
20 Aug 2021
Messages
169
Location
Market Harborough
Since energizing the Kettering to Wigston stretch is coming within the next few months, I presume that once it's done, the 810s will start testing shortly, followed by entering revenue service in early 2025. Is there still one section of wires missing (where the bridge demolition occurred)?
As of yesterday that section does not have any wires.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,603
As of yesterday that section does not have any wires.
However it does seem from the timelapse video to have all the registration arms etc already fitted. I think completion will be comparatively straightforward, and won’t be outstanding for very long?
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
1,719
Location
Nottingham
I assume they'd want to energise it as soon as possible, even if it's not brought into service. If only to deter cable theft.
 

Smoggy

Member
Joined
4 Aug 2009
Messages
69
Run down from Sheffield earlier and Down Rd looks complete apart from the small section mentioned above. Most of the contractor's compounds have been vacated also so the end must be close but do we have a target date yet for energisation.
Energisation is still scheduled for 28th July. Also today is the 1 year anniversary since Derby ECR went live.
 

InTheEastMids

Member
Joined
31 Jan 2016
Messages
739
Local media are reporting that the Newton Lane Bridge near Wistow will reopen by the end of the week.

The road linking Fleckney with Wigston is finally set to re-open this week after being shut for over seven months.

Work to replace a bridge over the railway on Newton Lane near Wistow should have been completed at the start of March, but was delayed when it was halted over concerns about the highway design.

Network Rail has told HFM the road will re-open ‘towards the end of the week.’

 