Yes, as has been stated repeatedly on this thread, with the June TT change.So is there any indication when we can expect services to start without some of the stops
Hang on, to passenger services as well??For the record, the new signalling between Bedlington and Ashington was brought
into use yesterday (Friday April 5th), with the first freight services to Lynemouth
and North Blyth to use the new signalling running this afternoon (biomass trains
are diverted via Morpeth until the end of May)
I understand that the line is now physically blocked at Bebside level crossing to
enable work to take place on the southern half of the route over the next six weeks
and if all goes well, the entire route will reopen on Thursday May 30th.
MARK
No. Although “runs as required” paths exist from the June timetable change, they’ll initially be for training. The passenger services won’t start until some weeks or months later. The website says “summer”, not “summer timetable”.Hang on, to passenger services as well??
The council are still going with the vague 'Summer 2024' line probably until the date is set in stone as they have had a bit of bad publicity around dates with Bedlington etc. They did state in an update that the Driver / Conductor training starts in April in the update about the removal of chase meadows crossing: https://www.northumberlandline.uk/post/closure-of-chase-meadows-foot-crossing . However as freightmaster has said the southern half is closed until May so seems that would be the more likely date for the training runs to start. They have been doing some already on the southern section and usually it looked like the paths (5A01/02 etc) dont appear on RTT until the day before the runs.
Apologies if this is in the wrong thread. Will Newcastle based Northern crews be learning the route to Ashington or will it be entirely crewed by the new Ashington depot?
Followed up by the Siemens Project ManagerFor the record, the new signalling between Bedlington and Ashington was brought
into use yesterday (Friday April 5th), with the first freight services to Lynemouth
and North Blyth to use the new signalling running this afternoon (biomass trains
are diverted via Morpeth until the end of May)
I understand that the line is now physically blocked at Bebside level crossing to
enable work to take place on the southern half of the route over the next six weeks
and if all goes well, the entire route will reopen on Thursday May 30th.
MARK
I am delighted to be able to announce that Siemens have successfully re-signalled and entered into service Phase 1 of the Northumberland Line on Saturday 6th April 2024 at 12:45. Over the Easter 2024 holiday period, during a 9 day blockade, Siemens undertook the first of 2 commissioning’s, entering into service 2 of 3 interlocking islands. This is a significant milestone for the overall project and is the key enabler for the introduction of passenger services later in 2024. We have seen some notable collaboration on-site throughout the blockade between CRSA, Morgan Sindall, AMCO, Network Rail and Northumberland County Council undertaking track renewals, highways upgrades, demolition of 2 signal boxes as well as the introduction of Siemens Signalling System. This stage has introduced a new WESTCAD workstation at Tyneside ROC, known as Ashington Workstation, decommissioned 3 mechanical signal boxes and converting Bedlington South signal box to a gate box, as well as replacing the semaphore signalling in the area for new LED Signals. Alongside this, we have upgraded a number of level crossings which will be operational and controlled by the new workstation, including MCB-OD MKII’s, CCTV, MCB and MSL crossings. The next part of the journey will see Siemens renew additional level crossings from Bebside to Benton, entering into service the final interlocking island in early June, bringing the southern part of the route into use. Upon completion of the final stage, the Northumberland Line will be in a position to introduce passenger trains back into service between Ashington and Newcastle. A huge thank-you to every single individual that has been part of the project team, I am so proud of what we have achieved together. There have been many challenges along the way but without the commitment and dedication shown over the last 2 years what we have achieved would not have been possible.
There’s a signal diagram link early last year, post #551, please see below. Bedlington South is mentioned in the following discussion.Is there a summary/diagram of the project showing what happens to the signal boxes and track layout please? Has Freeman’s SB on the Blyth branch gone, and has the triangle been simplified?
Why is Bedlington South remaining as a gate box - aren’t Isolated gate boxes a staffing headache (or not so bad as training is presumably easier)?
Thanks. Bit surprised the triangle is remaining as an old school double track one, but I guess if it ain’t broke don’t put it in your budget…..There’s a signal diagram linked early last year, post #551, linked below. Bedlington South is mentioned in the following discussion.
Northumberland Line reopening: progress updates
Its in the October Newsletter, piece by Northern on their recruitment and training says a Driver Team Manager, Conductor Team Manager and 20 drivers have been recruited and drivers have started route familiarisation with GBRF on their biomass trains. It also says the new CTM will be based at a...www.railforums.co.uk
A good question. Back in the earlier discussion I noted that a Modern Railways article had suggested it was going to be a fringe box to Tyneside, but that quickly turned out to be incorrect.Thanks. Bit surprised the triangle is remaining as an old school double track one, but I guess if it ain’t broke don’t put it in your budget…..
What’s special about Bedlington LC that it needs a bod on site to operate it?
I am far from an expert, but the staggered crossroads and high proportion of traffic likely to turn right immediately after crossing the line stand out to me as reasons why having a person may be preferable to CCTV or OD. The level crossing appears to be on a key route for Local traffic, although it's not clear whether routes traffic to/from further afield generally take would necessarily use the crossing.A good question. Back in the earlier discussion I noted that a Modern Railways article had suggested it was going to be a fringe box to Tyneside, but that quickly turned out to be incorrect.
The only thing I can think of is that it’s quite a complex area with crossings at both ends of the station, including the rail junction and a fairly busy foot crossing at the start of the Morpeth route as well. Not possible to reroute the roads like at Newsham. No footbridge so the only access between platforms seems to be via the road. Perhaps the combination of all those features makes it a higher risk area, but impossible to replace with technology such as obstacle detection?
Would be interesting to hear from an expert in such matters.
That looks like a drivers walkway to my very inexpert eye. The triangular stop marker is a reversing point, so presumably there's a foreseen need that long trains might be reversing behind the signal.I was over at Ashington earlier today and took a couple of photos from the soon to be demolished Wansbeck Square ramp and I noticed that a small section of the old Northbound platform has been resurfaced complete with yellow line but fenced off from the rest of the station. What appears to be a 7 car stop marker has been installed. Took a couple of photos below. Does anyone know what this would be for?
Emergency use for detraining if the bay can’t be accessed for some reason?I was over at Ashington earlier today and took a couple of photos from the soon to be demolished Wansbeck Square ramp and I noticed that a small section of the old Northbound platform has been resurfaced complete with yellow line but fenced off from the rest of the station. What appears to be a 7 car stop marker has been installed. Took a couple of photos below. Does anyone know what this would be for?
View attachment 156281
View attachment 156282
As Ashington is the end of the NR line, my guess (and its nothing more than that) is that the reversal facility is for test trains. As the line is now a passenger route it will presumably need to be inspected more frequently.Emergency use for detraining if the bay can’t be accessed for some reason?
It maybe allows for the ECS for the first few morning trains to run from the depot coupled as one? That doesn’t necessarily explain why it’s marked seven cars, but it might explain why some extra length at that particular location has been allowed for.Cant think of a reason why a 7 car train would end up there, the line is a dead end at a power station? Test trains would make sense, at 7 cars would the Network Rail HST fit? I doubt that would ever be used up there though.
Can confirm that the purpose of said drivers' walkway is for maintenance trains (think tampers, test trains, RHTTs etc.) which are otherwise too long to fit in the bay.That looks like a drivers walkway to my very inexpert eye. The triangular stop marker is a reversing point, so presumably there's a foreseen need that long trains might be reversing behind the signal.
Can confirm that the purpose of said drivers' walkway is for maintenance trains (think tampers, test trains, RHTTs etc.) which are otherwise too long to fit in the bay.
From what I can tell, only 950001 and an MPV would likely be able to squeeze in.
1Q35 runs every fourth Sunday - first booked run via Ashington is June 16th.Thanks for the info that explains it. I was having a browse of the proposed Ashington timetables in Realtime Trains and noticed this: https://www.realtimetrains.co.uk/service/gb-nr:H16441/2024-06-02/detailed (1Q35 Hull to Darlington via Ashington test train scheduled on 2/6/24) so it does look like they plan to send the New Mesurement Train up the Blyth and Tyne even though I realise it might not run...
Single Lead and only 1 signal for each direction (according to signalmaps https://signalmaps.co.uk/#newcastle:4465) so trains will only be able to pass without stopping on the actual ECML. Perfectly plausible though so long as the Up train's clear south of the junction that the Down train would get a clear road through to Northumberland Park.Youtube recommended to me a 10 year old cab ride video of Benton Junction to Morpeth Via Bedlington. I noticed the double track section as you leave Benton Jn is reasonably long, so can it be used as a ‘dynamic loop’ if down and up trains happen to be running at suitable times, or will one of the trains always be required to stop for a short period?