Presumably it wasn’t always like that?
On this type of junction where a branch curves away from a main line curving in the opposite sense, there is a tradeoff between speeds on the two routes. A junction without cant would allow more equal speeds and it was probably like that historically. However it has probably been re-designed in the meantime to give the main line a cant to allow higher speeds, which results in the branch having a negative cant and a lower speed. Reasons for this will be the need for journey time savings on the ECML, combined with trains that can reach higher speeds closer to Waverley, and the fact the diverging route was and still is less important.

It would most likelky still be possible to re-model for higher speeds on the branch but this would result in lower speeds on the main line, unless there is money and space for a major realignment of the whole junction.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,840
Location
Scotland
I criticised NR for not upgrading the pitiful 15mph speed across the busy ECML to & from the Borders railway when the geometry & location would allow it.
That's doubtful. As pointed out already, you have a branch curving away right from a high-speed line that is curving left. I'd be surprised if you could raise it to 25mph safely, never mind 40mph.
 

mcmad

Member
Joined
11 Mar 2015
Messages
979
I understand that plans being developed for a remodelling to allow for a simplified double junction with 40mph to Brunstane while retaining the 90mph mainline speed. Hopefully be delivered around 2021 or so.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,840
Location
Scotland
I understand that plans being developed for a remodelling to allow for a simplified double junction with 40mph to Brunstane while retaining the 90mph mainline speed. Hopefully be delivered around 2021 or so.
Does this involve making the mainline a 'double apex' curve so that the S&C is on a straight(ish) alignment? In any case, it doesn't sound like something that can be done with the stroke of a pen (as certain members seem to believe).
 

mcmad

Member
Joined
11 Mar 2015
Messages
979
No, its a full remodelling with the crossover moving North with new crossover onto the depot line to allow parallel moves onto the branch
 

railjock

Member
Joined
30 Jun 2012
Messages
373
On this type of junction where a branch curves away from a main line curving in the opposite sense, there is a tradeoff between speeds on the two routes. A junction without cant would allow more equal speeds and it was probably like that historically. However it has probably been re-designed in the meantime to give the main line a cant to allow higher speeds, which results in the branch having a negative cant and a lower speed. Reasons for this will be the need for journey time savings on the ECML, combined with trains that can reach higher speeds closer to Waverley, and the fact the diverging route was and still is less important.

It would most likelky still be possible to re-model for higher speeds on the branch but this would result in lower speeds on the main line, unless there is money and space for a major realignment of the whole junction.
Thanks.
 

XDM

Member
Joined
9 Apr 2016
Messages
483
I understand that plans being developed for a remodelling to allow for a simplified double junction with 40mph to Brunstane while retaining the 90mph mainline speed. Hopefully be delivered around 2021 or so.

Thanks mcmad. That is excellent news.

Do you mind if I ask your source?
Can we go to it to see the good news in detail?

I remain cynical, so many Network Rail plans never materialise.
 

och aye

Member
Joined
21 Jan 2012
Messages
804
A lot more progress has been made. Rails are both roughly half way down on both platforms. Just from a causal look, major heavy construction could be finished by the end of the year.
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,221
The whole project was meant to be finished by the end of the year. Fortunately the delay to the introduction of the Azuma means it doesn't need to be finished by then.
 

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
The whole project was meant to be finished by the end of the year. Fortunately the delay to the introduction of the Azuma means it doesn't need to be finished by then.

Doesn't hurt if they actually still manage to complete the project by 31st December though as it's still would give extra operational flexibility regardless of the Azuma being delayed.
 

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
Just checking but whereabouts would the buffers go in that picture?
 

Carntyne

Member
Joined
8 Jul 2015
Messages
883
It'll depend but they'll probably go where the white barriers are at the bottom of the picture.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
I've just noticed the steel sleepers in the first photo seem to be spaced at a greater pitch than I remember seeing the concrete ones at the east end. Is this because it's only intended to be occupied by light passenger services at low speed or is it temporary works to get engineering trains in and will be replaced by concrete sleepers in due course?
The latest picture seems to suggest that track has gone, I suspect you’re probably right that it was temporary.
 

GrimShady

Established Member
Joined
13 Dec 2016
Messages
1,740
Weren't these platforms for the extra services VTEC planned to run?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
It'll depend but they'll probably go where the white barriers are at the bottom of the picture.
I think they might be further away. I think someone posted way back in this thread that there’d be what’s known as a “frangible deck” over the overrun behind the buffers. Allows the maximum circulation space, but the buffers can slide into it in extremis.

Looked back now and the info is available via the link to Edinburgh planning dept in post #12.
 
Last edited:

385001

Member
Joined
27 Nov 2017
Messages
211
Location
Edinburgh
Network Rail has published some fascinating photos of the work on Twitter including the old Nor" Loch sewer!

https://twitter.com/NetworkRailSCOT/status/1063470398967300104

Network Rail said:
Great progress is being made on the extension of platforms 5 & 6 at #Edinburgh #Waverley station.

Engineering trains are being used to bring in materials to #Edinburgh #Waverley, including the precast units used to create the walls for platforms 5 & 6.

The excavation of platform 6 at #Edinburgh #Waverley station has uncovered the old Nor' Loch sewer which runs under several of the platforms within the station.

DsIxqQKX4AAGKAd.jpg
DsIxqQKXQAASWvK.jpg

DsI0ZnYWkAEaxeO.jpg

DsI0a0vWwAAIJQh.jpg

DsI0btnXoAAF3rr.jpg

DsI0dYEWsAEHxJO.jpg

DsIzhEuWoAAJfnz.jpg
 

Photohunter71

Member
Joined
17 Jan 2012
Messages
576
Location
In a flat beside Niddrie West junction
How much more capacity could the station potentially take until there's a clamour for another major station in Edinburgh. The reason I ask is, I was driving along the Western approach road a couple of days ago, I turned to my wife and said that we were driving on the old caley lines and I wonder how long it will be until they fully regret not having kept them available. Where, if possible could another "Haymarket" Sized station be placed in Edinburgh?
 

Jorge Da Silva

Established Member
Joined
4 Apr 2018
Messages
2,592
Location
Cleethorpes, North East Lincolnshire
How much more capacity could the station potentially take until there's a clamour for another major station in Edinburgh. The reason I ask is, I was driving along the Western approach road a couple of days ago, I turned to my wife and said that we were driving on the old caley lines and I wonder how long it will be until they fully regret not having kept them available. Where, if possible could another "Haymarket" Sized station be placed in Edinburgh?

I know there is a couple of disused platforms still. One between platform 3 and 4 and another between 3 and 2. Other than that there is very little they could change for additional capacity.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
I know there is a couple of disused platforms still. One between platform 3 and 4 and another between 3 and 2. Other than that there is very little they could change for additional capacity.
If you go back through this thread somewhere there’s quite a discussion (with links) about NR’s route study including plans to join existing bay platforms together through the station, and also to add a third line through the disused tunnel on the approaches, all about improving capacity. Around about post #643
 

47271

Established Member
Joined
28 Apr 2015
Messages
2,983
How much more capacity could the station potentially take until there's a clamour for another major station in Edinburgh. The reason I ask is, I was driving along the Western approach road a couple of days ago, I turned to my wife and said that we were driving on the old caley lines and I wonder how long it will be until they fully regret not having kept them available. Where, if possible could another "Haymarket" Sized station be placed in Edinburgh?
The value of a reinstated Princes Street station was discussed in this thread around a year ago.
https://www.railforums.co.uk/threads/princes-street-station.158482/
Returning the West Approach to rail use might not be quite as productive as it first appears.
 

KGC

New Member
Joined
16 Oct 2018
Messages
2
Presumably any future HS line will have to enter Waverley from the East due to capacity issues. Given the length of platform required, would this mean building on the current car park or is the current setup able to accommodate? I'd also be interested to know the best approach route - would it be feasible to rebuild the eastern/southern section of the south-sub for HS connected to a new line running south? I know there's been a lot of discussion surrounding eastern approaches, capacity issues and the south sub line, but am just curious (from a non expert's point of view!) about what is and isn't possible.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
Regarding the first picture in post #771, and the update in post #773 above, does anyone know the exact purpose of the huge concrete block on the right (P6 side), I assume there’ll also be a matching one on the other side at the same position. The first pic shows a foundation on the P5 side. They seem to be alongside where I’d expect the buffers to be positioned.

Is it possibly part of the support for the side girders of the frangible platform area? Or a foundation for something else, perhaps an OHLE portal?
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,840
Location
Scotland
Regarding the first picture in post #771, and the update in post #773 above, does anyone know the exact purpose of the huge concrete block on the right (P6 side)
My first though was that it is a precast box for underground services access.
 