Observations from today starting with Maidenhead to Twyford, Mains only.
Airport Jn to Maidenhead wires go through the station for a short distance. There is then a short gap before the wires commence again. This is more advanced (towards Reading)on the UM than the DM. This finishes part way to Ruscombe. As far as Ruscombe all the registration arms are then fitted.
From Ruscombe to Twyford the masts are up but no registration arms and one portal missing at Twyford east.
No change through Twyford station.
DR/UR from Twyford to Kennet bridge: still some registration arms required to Lands End, then steel work looks complete to just before the bridge. Return conductor up most of the way through Sonning cutting.
DM/UM: no registration arms to Lands End and some missing through the cutting, includes one mast still in the cess. From the end of the cutting to Kennet bridge still some steel work to go but most up.
Over Kennet bridge no r/arms have been fitted. A few then missing DM/UM to just before New Jn.
From New Jn through the station, over the flyover, and on the reliefs to connect with existing wires at Tilehurst E, most of the steel work looks to be up.
There are no r/arms fitted through plat 15 yet. 13 & 14 are wired already.
1 to 3 & 7 to 12 look about ready for the wires.
Electrification to Land's End, you've started something now!