Apologies if this has already been asked (I did look), but have their been any further announcements Bristol Temple Meads and Bath since it was paused? I understand there is a sensible order to do things in, but if the resignalling is going to be complete within the next six months, surely now is the time to be planning what is needed for the electrification (for example, would they want a possession over Easter 2019).
- Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018; Temple Meads to Both in October 2018), track remodelling and Filton Bank 4-tracking (to be completed by December 2018).
Or is paused just a nice way to say cancelled?