Great Western Electrification Progress

Status
Not open for further replies.

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,447
B&H photo updates, Reading West.

Tilehurst Rd bridge now single file controlled by lights.
DSC01538.JPG DSC01539.JPG

Reading West platform extension to finish.
DSC01540.JPG
Theale, Aldermaston & Thatcham all open.

Looks to still be some snagging on the overheads.
DSC01542.JPG

Signs up both ends of the platforms. Also at other stations with a smaller versions noted at Newbury.
DSC01543.JPG DSC01556.JPG

For those who like to ponder on things, how long before any of the following change?
DSC01541.JPG
Remains of the old footbridge with OFF indicator.
Temporary cable bridge.

DSC01544.JPG DSC01545.JPG DSC01546.JPG
Temporary looking access to Oxford Rd on the down side.

Probably all dependant on what happens about a footbridge!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Better, though, to wire them now than having to come back once Newbury-Taunton (and obvs Taunton-Bristol) has a business case

Be interested to know in which millenium you think that's going to happen!

Looking at 3973EXL's latest pictures, what does that black and white board on the fence at the end of the Newbury platform mean?
 
Last edited:

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,447
B&H Newbury

Country end platform signs.
DSC01556.JPG
Pan down sign on platform 1 not fixed yet. Supporting a lamp post at the moment.

Up through Banner repeater.
DSC01557.JPG

Rockingham Rd bridge. Parapets are about 5' high.
DSC01554.JPG DSC01551.JPG

Anti-personnel protection.
DSC01550.JPG

Given the bridge parapets on Rockingham Rd, No electric traction beyond this point signs on the platforms and a neutral section just west of the platform, a suspicious person might begin to wonder!
DSC01548.JPG DSC01549.JPG
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,446
Still think the sign about access forbidden “unless wires are dead” is over the top. Someone did suggest earlier it was wrong for that location though.
 

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
2,730
Location
81E
The early hours of Sunday 7th (turning back at Chipping Sodbury) and then Friday 19th of October between Parkway and Wootton Bassett.The final, fastest runs were made under headcodes 5Z78 and 5Z57 respectively.

Thanks.

I was at work that Sunday as well, probably presumed the ECS moves were just mileage accumulation runs. Good to hear the OLE testing has started.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
Look out for down trains running with pantographs raised between Causeway Crossing and Swindon station from this Sunday...

(Note, pantographs will still be lowered at Moreton Cutting, and diesel mode selected, but may be raised again just after Causeway Crossing.)
 

DaveHarries

Established Member
Joined
12 Dec 2011
Messages
2,298
Location
England
Look out for down trains running with pantographs raised between Causeway Crossing and Swindon station from this Sunday...
Will the be in service or merely testing? Either way I am hoping that electrics will be on by the time I go to London for the day on 17th November as the last time I did London we were diesel from Didcot Parkway, where I had parked my car, to Paddington.

Dave
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,355
Will the be in service or merely testing? Either way I am hoping that electrics will be on by the time I go to London for the day on 17th November as the last time I did London we were diesel from Didcot Parkway, where I had parked my car, to Paddington.

Dave

They should - unit restrictions allowing - all be Electric from Didcot to London.
 
Joined
13 Feb 2011
Messages
1,063
Location
Cardiff
Some substantial foundations for masts have appeared on the four corners of the rail bridge over St Mary's Street in Cardiff (and there is ongoing work behind the nearby OU building). I think we can expect to see some masts erected in this area shortly.
 

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
2,730
Location
81E
Look out for down trains running with pantographs raised between Causeway Crossing and Swindon station from this Sunday...

(Note, pantographs will still be lowered at Moreton Cutting, and diesel mode selected, but may be raised again just after Causeway Crossing.)

Will the be in service or merely testing? Either way I am hoping that electrics will be on by the time I go to London for the day on 17th November as the last time I did London we were diesel from Didcot Parkway, where I had parked my car, to Paddington.

Dave

From the 28th October 80x trains running DOWN passenger trains can use the OLE between Causeway Crossing & Swindon.

The OLE between Foxhall Jn & Causeway and that west of Swindon Station is still not authorised for passenger service so down trains will ‘pan down’ at Moreton Cutting as norm then ‘pan up’ at Causeway.

Down trains not stopping at Swindon will revert to diesel mode prior to the station, stopping trains can switch to diesel during the station stop.

80x units may be observed with ‘pan up’ between Didcot & Steventon and between Swindon & Bristol Parkway but these will be ECS involved with the OLE testing.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,498
Location
Between Peterborough & Bedlington
From the 28th October 80x trains running DOWN passenger trains can use the OLE between Causeway Crossing & Swindon.

The OLE between Foxhall Jn & Causeway and that west of Swindon Station is still not authorised for passenger service so down trains will ‘pan down’ at Moreton Cutting as norm then ‘pan up’ at Causeway.

Down trains not stopping at Swindon will revert to diesel mode prior to the station, stopping trains can switch to diesel during the station stop.

80x units may be observed with ‘pan up’ between Didcot & Steventon and between Swindon & Bristol Parkway but these will be ECS involved with the OLE testing.
What's the holdup on the UP side?
 

BillZabet

New Member
Joined
25 Oct 2018
Messages
2
Does anyone know whether the route between Chippenham and Bath Spa is still being electrified or has it been deferred/postponed/scrapped?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,746
Location
Leeds
For those of us not familiar with the line and lacking the relevant Quail, where's Causeway Crossing, please?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,746
Location
Leeds
Does anyone know whether the route between Chippenham and Bath Spa is still being electrified or has it been deferred/postponed/scrapped?

The planned electrification of the route was cut back to Thingley Junction in late 2016 and has since been cut back further to Cocklebury Lane, just east of Chippenham.

Electrification of the missing routes Cocklebury Lane - Chippenham - Thingley - Bath - Bristol TM and Bristol TM - Filton may possibly be resurrected during Control Period 6 which begins next April.

Welcome to the forum, by the way.
 

BillZabet

New Member
Joined
25 Oct 2018
Messages
2
The planned electrification of the route was cut back to Thingley Junction in late 2016 and has since been cut back further to Cocklebury Lane, just east of Chippenham.

Electrification of the missing routes Cocklebury Lane - Chippenham - Thingley - Bath - Bristol TM and Bristol TM - Filton may possibly be resurrected during Control Period 6 which begins next April.

Welcome to the forum, by the way.

Thanks.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
What's the holdup on the UP side?

No hold up per se, Network Rail just want to ensure everything runs smoothly in the down direction before allowing up trains to do the same. Up trains should be able to use the wires through the same section from the following week (Sunday 4th November).
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,498
Location
Between Peterborough & Bedlington
No hold up per se, Network Rail just want to ensure everything runs smoothly in the down direction before allowing up trains to do the same. Up trains should be able to use the wires through the same section from the following week (Sunday 4th November).
Ahh I gotcha. NR seem to be doing a "belt and braces" approach, which - given the OLE furore at West Ealing/Hanwell last week - is admirable and understandable!
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,447
There is still bridge work in progress east of Reading.

Butts Hill Rd (Sonning Cutting)
DSC01558.JPG
Road restrictions started in 2017. Work to finish 31/10/18 according to notice posted on site.
Going to be a busy few days to achieve this!
DSC01559.JPG DSC01560.JPG DSC01561.JPG

Southbury Lane Ruscombe
Top of the parapets to finish, plus wing walls.
DSC01562.JPG DSC01563.JPG DSC01564.JPG DSC01565.JPG DSC01566.JPG DSC01567.JPG
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,498
Location
Between Peterborough & Bedlington
GWML Electrification: State of Play, as of 29/10/18.
All mileages given from Paddington, except where noted.
Paddington to Wootton Bassett Jct - LIVE
  • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. The envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
  • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
  • Everything wired at Swindon; P1-4, and the Through Road. Switchgear at the Bristol end of P1-4 is now live.

Small Points
  • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
    • In preparation for the Elizabeth Line running to Maidenhead, Hayes & Harlington to Maidenhead was closed off over the Early May Bank Holiday (5/5 to 7/5); this included renewals of S&C at West Drayton & Slough West Jct, alongside HOPS work at Langley. Paddington to H&H was also closed on May 6th, and encompassed final OLE works for Crossrail, alongside (presumably) ATF installation, finishing of Platform Extensions, lift shaft installation, passenger footbridge installation, and ticket hall foundation installation.
  • At Ealing Broadway, the staircase to P2/3 is being demolished and replaced with a new structure as part of the Crossrail works. Access is via the footbridge at the London end from P4 - work started on 1/10 and should continue until late December.
  • Parapet Work ongoing at Southbury Lane Bridge, Ruscombe; the top of the parapets & the wing walls remain unfinished.
  • Parapet Work has yet to commence on Butts Hill Rd Bridge, Woodley; restrictions are due to be lifted by Hallowe'en so there's not much time to spare!
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of wires for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
  • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are now authorised for passenger service for Down trains ONLY; the discussion continues.
  • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
  • Another note on the OLE beyond Didcot: the wires west of Causeway Crossing are now authorised for passenger service (as of Sunday 28th October) as far as Swindon - for DOWN (westbound) trains ONLY. (The UP line is due to follow on the 4th of November.) Trains may run on AC under test conditions (as ECS) beyond to Wootton Bassett & Bristol Parkway, but entry of IETs in AC passenger service beyond Swindon is unlikely before December.

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge)
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • All masts and earth wires are now up between Wootton Bassett Jct & Cocklebury Lane Overbridge.
  • The Up Line is wired throughout from Cocklebury Lane to Wootton Bassett.
  • The Down Line is fully wired apart for a half-mile gap in both catenary & contact wires from Dauntsey to Christian Malford.

Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
  • Piles continue westwards to the next bridge.

Thingley Jct - Keynsham
  • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
  • Both Box & Middle Hill Tunnels have had track lowered.
  • A new footbridge has been built at Ashley Box.
  • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
  • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 but is not yet in use.
  • Bath Spa platforms realigned & raised, with track also slewed.
  • Track through Oldfield Park & Keynsham now lowered.
  • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct to Filton Jct (inc. Bristol Parkway) - LIVE
  • All catenary & contact wires up from Wootton Bassett Jct, past Westerleigh Jct (107m 14ch) through Bristol Parkway and thence to Filton Jct & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
  • BPW Platforms now fully wired; includes the Down Goods Loop & Up Passenger Loop.
    • A number of masts & booms (now all wired up) are up on the line towards Filton Abbey Wood, between Stoke Gifford Jct No.1 (111m 79ch) and Filton Jct No.1 (113m 01ch); these end just short of Filton Jct 1 and will presumably act as an overrun until electrification continues into Temple Meads.
    • Section Isolator Masts now installed immediately before Stoke Gifford Jct No. 1, for the proposed neutral section just west of Bristol Parkway; these now have their feeder wires.
  • Filton Bank bridge works (mileages all from Temple Meads):
    • Easton Rd Overbridge (1m 18ch) completely rebuilt.
    • Narroways Footbridge (2m 12ch) replaced.
    • Ashley Hill Footbridge (3m 11ch) replaced.
    • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
    • Footbridge south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
Filton Jct - Severn Tunnel
  • The Patchway/Severn Tunnel Blockade is now complete.
  • The 3-week Bristol Parkway Blockade and subsequent weekend blockade are also now complete.
  • Stoke Gifford IEP Depot all wired.
  • Patchway Tunnels conductor rail installed.
  • Masts, booms and SPS up through Patchway. No wires yet.
    • Cattybrook Brickworks Bridge closed as of 18/3/18.
  • At Pilning, during the Summer Tunnels blockade, all portals and masts have now been erected, and wires have gone up.

Severn Tunnel - Newport
Due to have IETs in AC service by 2020!
  • Severn Tunnel Conductor rail in place. A number of masts on both sides of the line are now up at Caldicot, just before the Western tunnel mouth; these now extend westwards towards the eastern end of the platforms at STJ.
  • Part of the central island platform at Severn Tunnel Junction has been fenced off - a possible mast location?
  • All bridge rebuilding complete from Severn Tunnel Jct (149m 14ch) to Bishton Flyover (152m 30ch).
  • Masts beginning to go up between Severn Tunnel Jct & Bishton Flyover, as of 3/4/18. These include:
    • At least 11 between Undy (Playing Fields Footbridge) and the M4 viaduct over the mains; one just east of the "white house" has a TTC boom. It can be assumed that its 8 comrades will be similarly adorned. Another mast over the Reliefs west of the "white house" has now gained a TTC boom with 1 SPS assembly; it has a twin over the Mains.
    • Two large uprights have gone up between Undy Playing Fields footbridge & "the ramp" bridge at Magor on opposite sides of the line; these may well take a portal boom.
    • Another 3 masts (two for a portal boom, one a TTC with boom up) have appeared east of "the ramp" bridge at Magor; these join the sole TTC on the Up side by the bridge.
    • The 3 TTCs west of "the ramp" bridge (2 on the Down, 1 on the Up) have gained SPS.
    • The signal gantry at Magor (west of the West End Footbridge) has been replaced by 4 signals on posts; this should mean its removal prior to electrification is imminent. A TTC with SPS is up over the Mains there too.
    • 1 mast is up to the west of Redwick Rd Bridge (by the Down Relief), and a mast due to bear a portal is up to the east of Whitewall Footbridge (by the Up Main). OTP is in place for a piling/masting operation by Redwick Rd compound.
    • Masts (with SPS fitted) up between Bishton Flyover (including over it) and Llanwern West Jct (156m 20ch). 5 masts are currently up on the curve down from the flyover at its eastern end.
    • Plenty single masts (with SPS fitted & folded) up along the Mains between the Flyover and Bishton LC. A run of Earth wire is now up on the Up side at Bishton.
  • West of Bishton LC (153m 01ch), masts are around 90-95% up (all bar a few have booms and SPS), with the main gap at Llanwern Works East Connection (153m 05ch). This continues west towards Llanwern Works West Connection/Llanwern West Junction (156m 03ch to 156m 20ch).
  • Some masts have sprouted near Lliswerry pond.
  • 6-track portals, probably TGBUs (aka Thumpin' Great Big-Uns) going up aroung East Usk Yard (approx. MP157 1/2).
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
  • Caerleon Rd Overbridge to be refurbished in 2 phases - 20/7 to 30/11, and then January ‘19 to March ‘19. Not sure what impact on wiring this will have.
  • Some SPS has now gone up between Maindee West & Maindee East; between Maindee West Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford; the ELR for the southern part of the Marches Line), masts with TTCs on are also going up (as overruns) over the Marches Line; the termination mast & associated TTC are just north of signal "NT 1559".
  • Fixings for masts have now been installed on the Usk Bridge.

Newport
  • All canopies now cut back.
  • Masts and portals now appearing at the western end of the station, some with SPS attached. More started to appear in mid-April; additionally, two at the Cardiff end & two through the P1 canopy on the weekend of April 28th/29th.
  • 4-track portal now up over the southern 4 tracks, just east of the new station footbridge.
  • Two six-track portals have now gone up over the western throat of the station, just short of a 4-track portal (uprights of) & a TTC (with SPS) adjacent to Clytha Park Rd.
  • Old stn footbridge now removed; 4-track portal of the "TGBU" (Thumpin' Great Big 'Un) variety has been installed in its place.
  • A new portal has gone up at the east end of Newport, with all the fixings for switchgear affixed at the top. Droptubes for registration arms are also on.

Newport - Cardiff
  • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
    • one by the Down Relief;
    • two by the Up Main (one of which is a boomed TTC with SPS);
    • three by the Gaer Jct - Park Jct Chord.
  • Around 6 piles are in adjacent to the Up Main between Gaer Jct and Ebbw Jct (160m 07ch); these will probably take masts for portal booms. One such boom appears to have gone in! Currently unknown if Alexandra Dock Jct Yard will be electrified.
  • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
  • Over 100 masts from Ebbw Jct to Marshfield (163m 60ch). Booms & SPS starting to appear in the area too.
  • Green Lane Bridge, nr Marshfield (164m 57ch) reopened to traffic after reconstruction. Masts (with SPS) up around here too.
  • Lots of masts (with booms, SPS & ATF brackets) now up near Mardy Rd Bridge, Rumney.
  • Two TTCs, one on each side of the tracks, have been erected by the bridge at Rhymney River Bridge Jct (167m 61ch).
  • About 4 or 5 portals have been erected just west of Pengam Jct (168m 40ch); 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side. Some of the portals now have booms, and bear SPS; one of these has all its registration arms up.
  • First Welsh Wire Run: 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs on the 15-16th September 2018; this is assumed to be a crossover as it crosses from one Relief line to the other.
  • A handful of masts are also up around Long Dyke Jct; some have now gained TTC booms and SPS as well.
  • Substantial mast foundations have appeared at each corner of the bridge over St. Mary's Street in Cardiff, along with work behind the nearby OU bldg. Masts may be imminent.
  • Splott Rd Bridge upgrade work now complete.
Cardiff Central - Platforms 0-4 to be wired
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • Piling underway at the extreme ends of P1/2 & P3/4 for future masts. One can assume portals will bridge the gap between P2 & P3, over the Through lines.
  • Canopy cut-back work now underway on P2.
  • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
  • Plenty piles up adjacent to Cardiff Canton.
  • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s.
  • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up but no wires.

GWML/SWML Blockades:
  • 6/7 to 3/12: Reduced capacity between Newport & Cardiff Central while electrification progresses; assume only 1 pair of lines open at a time.
  • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway blockaded to allow OLE to be installed within the station; done.
  • 27/10 to 18/11: Filton Bank blockaded for 4-tracking; worth posting on here as *some* OLE works might occur - not that I know for certain.
  • 11/11: Bristol TM to Bath Spa blockaded until 13:00 while the resignalling work is completed on this stretch.
  • 25/12/18 to 1/1/19: Bristol Parkway - Newport will be blockaded again, due to electrification work at Severn Tunnel Junction.
  • More Blockades will follow; details as they become available.

Berks & Hants Line (Reading-Newbury) - LIVE
ALL WIRES NOW UP. Electric trains are set to be in squadron service from January 2019 - ORR sign-off due around Christmas.
  • Wires from Oxford Rd Jct are now LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) as of 0650 on 21/10/18.
  • EMUs to Newbury on test SOON - IETs likely to be first (as they're already route-cleared), with 387s and 319s to follow. Platforms will need to be gauged.
  • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
  • Extension to Reading West Up platform nearly complete. Earth wires are still missing here & there, and final dropper adjustment needs to be undertaken.
  • Parapet work now complete on the A4 (Bath Rd) overbridge. Similar works for Tilehurst Rd overbridge are now underway; the bridge has now been reduced to single-lane workng for road traffic.
  • Platform extension works complete (and now opened) at Theale, Aldermaston and Thatcham.
  • Newbury's new footbridge is now open (not the lifts yet).

Limit of Wiring: 53m 42ch.
  • Gives Ample room to reverse a 12-car 387 formation.
  • Immunised signalling continues to about MP55 1/2. Bedwyn Turnback Siding now extended to accommodate 5-car IETs.

Project Postponements
  • Thames Valley Branches: Windsor & Henley deferred to CP6. Marlow removed from scope of current programme. The first few yards of each branch (bar the Henley Branch) have been wired as an overrun.
  • Southcote Jct to Basingstoke has also been deferred to CP6.
  • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until (presumably) CP6; presumably this will wait until Bath-Bristol resignalling is complete. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018; Temple Meads to Bath in November 2018), track remodelling and Filton Bank 4-tracking (underway - to be completed by December 2018).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too).
 
Joined
9 Nov 2017
Messages
260
Good to see electric services to Swindon today (albeit only in one direction - UP services expected next week). I'll try and get a photo today of a raised pan in the station if I can.
 

Southsider

Member
Joined
10 Aug 2015
Messages
759
Part of this, part of Shotts and Stirling, Dunblane and Alloa all going live on 4 Nov. I hope the national grid is ready!
 

Dren Ahmeti

Member
Joined
17 Oct 2017
Messages
550
Location
Bristol
There is a test path in the system for a 5 car 800 on the 31st October: 5Z40 North Pole - Kennington Goods Loop will then run 5Z41 Kennington Goods Loop - Bedwyn Reversing Siding, stopping at all stations bar Reading and Didcot Parkway, which will then run 5Z42 Bedwyn Reversing Siding - London Paddington, stopping at some stations on the B&H, which then forms 1C23 2x5 at Paddington.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,355
There is a test path in the system for a 5 car 800 on the 31st October: 5Z40 North Pole - Kennington Goods Loop will then run 5Z41 Kennington Goods Loop - Bedwyn Reversing Siding, stopping at all stations bar Reading and Didcot Parkway, which will then run 5Z42 Bedwyn Reversing Siding - London Paddington, stopping at some stations on the B&H, which then forms 1C23 2x5 at Paddington.

There is a test train running, but it doesn’t then form 1C23 - it goes ECS back to the pole at 16+44.
 