GSoP Post 33.0 - tying up loose ends
Manchester Victoria - Preston; State of Play, week beginning 17th December 2018.
All wire runs up and LIVE!
Speed changes still seem to be postponed, despite all wires being live. Test runs with both a 390 & a 319 seemed to have gone without a hitch. Any outstanding points are highlighted in red.
All mileages from Manchester Victoria. Bridge mileages are approximated where noted.
1. Man Vic Station (Platforms 3-6) - Man Vic West Jct - Deal Street Jct; 0m 0ch to 0m 32ch
Fully wired and energised 2013-15.
(N.B. Platforms 1 & 2 at Man Vic have now been bedanglied; more masts may still need to be installed at the east side of Man Vic before wires can go up over all lines; however this is not considered as part of this programme. Wires due to go up here over Christmas, in conjunction with the installation of the "Great Extension Lead" from Stalybridge.)
2. Deal Street Jct - Windsor Bridge South Jct; 0m 32ch to 1m 46ch
Fully wired and LIVE as of 1/10/18. Wires overlap into the CEMEX sidings (Hope Street). At Salford Central, the westbound (Down) platform has had RSC ducting installed at shin height.
Protruding roof beams were also cut back to facilitate the addition of wires. With Salford Central now wired, all wires are up from Manchester Victoria & Manchester Piccadilly to Euxton Jct.
3. Windsor Bridge South Jct - Windsor Bridge North Jct (inc. Salford Crescent); 1m 46ch to 1m 70ch
Salford Crescent station is fully wired; this includes all crossovers & lines. Wires are also up on the overruns along the Atherton Line.
4. Windsor Bridge North Jct - Bolton (South End); 1m 70ch to 10m 50ch
At Agecroft, there are a couple of masts (sans wires) in the bush alongside the sidings, leading to a terminal gantry with very odd attachments. Do these now have wires?
At Clifton, Drainage manhole modules are awaiting installation; temporary covers are over their future homes. Have these been installed?
Bridge MVE1 27B (immediately NW of the M60 overbridge) is now open.
5. Bolton Station; 10m 50ch
Canopies look complete, and platforms now fully open. All wiring is complete, both on the main lines, the side platforms and the overrun towards Blackburn.
UTXs wait to be installed in the works compound west of the track off Platform 5. Have these been installed?
6. Bolton (North End) - Euxton Jct; 10m 50ch to 25m 31ch
C&C wires up on the overlap on both Wigan lines until the Limit of Wiring.
Platform extension/resurfacing work complete on the Down platform and the Up platform at Lostock.
The arrangements at Lostock ATF station were designed to support the electrification to Wigan, so the UTX was sized to take four feeder cables to the proposed neutral section located towards Westhoughton. Two feeders for each track, one each side of the NS. Wigan-Lostock has no AF, classic boosterless only.
Orangemen at work on the footpath at the foot of the northern steps of Heath Charnock FB. Has this concluded?
Do let me know if I've missed anything!