• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

East-West Rail (EWR): Consultation updates [not speculation]

Status
Not open for further replies.

richieb1971

Established Member
Joined
28 Jan 2013
Messages
1,981
I thought the Bletchley flyover was mostly the reason the EWR project was financially viable in the first place. To replace most of it seems to have eradicated any advantage it gave in the first place.
I guess it was in poor condition for trains to go over it, rather than trains go under it. Or did the EWR team just find out its a liability on both fronts?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,946
Location
Nottingham
I thought the Bletchley flyover was mostly the reason the EWR project was financially viable in the first place. To replace most of it seems to have eradicated any advantage it gave in the first place.
I guess it was in poor condition for trains to go over it, rather than trains go under it. Or did the EWR team just find out its a liability on both fronts?
Network Rail would be inspecting it periodically, not just the spans that went over roads or other lines, because of the safety risk if it had collapsed. But being safe to support itself doesn't mean it's safe to support a train, or in the worst case a train on each track. I don't think we know when it was established that parts of it needed replacement, or how many such replacements were budgeted for in earlier stages. They might even have assumed the whole lot would need doing, so any parts that remain represent a saving!
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,473
Network Rail would be inspecting it periodically, not just the spans that went over roads or other lines, because of the safety risk if it had collapsed. But being safe to support itself doesn't mean it's safe to support a train, or in the worst case a train on each track. I don't think we know when it was established that parts of it needed replacement, or how many such replacements were budgeted for in earlier stages. They might even have assumed the whole lot would need doing, so any parts that remain represent a saving!
The Planning application to replace sections was comparatively recent, (Dec 2019) and it certainly read as though they had fully expected to use the existing viaduct following a certain amount of maintenance and waterproofing work.
 

mwmbwls

Member
Joined
14 Dec 2009
Messages
648
Yes - that was the original plan but the inherent nature of reinforced concrete with the interplay of reinforcing bars, cement and aggregate is always complex. Every atom of steel has a the ambition of growing up to be rust and having done they pass it on to their chums. Thinking about maintainabilty as well as constructability now plays a larger part in life cycle calculations.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,225
I thought the Bletchley flyover was mostly the reason the EWR project was financially viable in the first place.

In a billion pound project, the difference between a significant refurbishment and partial reconstruction of one flyover is basically ‘noise’ in the cost.
 

The Ham

Established Member
Joined
6 Jul 2012
Messages
10,335
Hmm, let's hope the electrification happens quickly then, since taking a diesel train instead of an electric car wouldn't decarbonise much ;)

Taken as an average 10,000 miles on the UK railways the per passenger emissions are 0.59 tonnes.

This compares with 0.60 tonnes for EV's.

However even that comparison isn't that great as there's a load of miles which people will drive that they can't go by rail, if those are mostly done by walking/cycling then that drops the emissions further for rail.

You also have to bear in mind that the maintenance of the railways (9,800 miles worth) produce less emissions than the maintenance of the strategic road network (4,800 miles).
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,403
Yes - that was the original plan but the inherent nature of reinforced concrete with the interplay of reinforcing bars, cement and aggregate is always complex. Every atom of steel has a the ambition of growing up to be rust and having done they pass it on to their chums. Thinking about maintainabilty as well as constructability now plays a larger part in life cycle calculations.
The issue is with the bearings where the support beams weren't perpendicular to the viaduct alignment. Hence replacing those sections as well as the adjacent ones.

Highways England have plenty of similar issues...
 

camflyer

Member
Joined
13 Feb 2018
Messages
878
Yes - that was the original plan but the inherent nature of reinforced concrete with the interplay of reinforcing bars, cement and aggregate is always complex. Every atom of steel has a the ambition of growing up to be rust and having done they pass it on to their chums. Thinking about maintainabilty as well as constructability now plays a larger part in life cycle calculations.

Of course, to be pedantic, there is no such thing as an "atom" of steel as it is an alloy.
 

jfowkes

Member
Joined
20 Jul 2017
Messages
897
Forgive me if this has been asked before, but was the viaduct expected to be this bad? It's not a terribly old structure is it? Was the deterioration worse than expected or was it at the end of its design life anyway?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,403
Forgive me if this has been asked before, but was the viaduct expected to be this bad? It's not a terribly old structure is it? Was the deterioration worse than expected or was it at the end of its design life anyway?
Worse than expected in one particular area (the bearings) and the bridge decks would have had to be jacked up in pairs (twice per deck) to address hence very disruptive to the WCML undeneath.
Generally in quite good condition.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,225
Plenty of civils and structures work to do (and no sign of it starting) before it is worth laying any track, I'd go for first track in 2022

Agreed. Track is one of the last things to do. A year before opening probably.
 

DelW

Established Member
Joined
15 Jan 2015
Messages
3,896
Forgive me if this has been asked before, but was the viaduct expected to be this bad? It's not a terribly old structure is it? Was the deterioration worse than expected or was it at the end of its design life anyway?
Around 60 years old, which is a fairly typical design life for an RC structure. Plenty of motorway bridges of that era have needed major repairs or replacement.
It's often the ancillaries which fail (e.g. bearings, expansion joints) which then cause adverse effects on the main structural elements.
 

BrianW

Established Member
Joined
22 Mar 2017
Messages
1,465
Re Bletchley viaduct- It could have been worse. It could have been a 'listed' structure needing to be kept for posterity- after all it was surely of historical interest having been closed so soon after opening- maybe a record? I don't know dates or comparotors- maybe a Forumite (like Bletchleyite maybe?) will advise? Has the Concrete Society not complained?
 

The Ham

Established Member
Joined
6 Jul 2012
Messages
10,335
Apparently rather as an alloy has not atoms (see above) concrete cures rather than sets :frown:

Which is why I resisted referencing rods for their own backs, as as it's bars and generally someone else makes them.
 

mwmbwls

Member
Joined
14 Dec 2009
Messages
648
Around 60 years old, which is a fairly typical design life for an RC structure. Plenty of motorway bridges of that era have needed major repairs or replacement.
It's often the ancillaries which fail (e.g. bearings, expansion joints) which then cause adverse effects on the main structural elements.
The viaduct was built between 1958 and 1960 as part of the WCML electrification programme. The overhead at that time was fixed directly to the viaduct.
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
29,325
Location
Fenny Stratford
I thought the Bletchley flyover was mostly the reason the EWR project was financially viable in the first place. To replace most of it seems to have eradicated any advantage it gave in the first place.
I guess it was in poor condition for trains to go over it, rather than trains go under it. Or did the EWR team just find out its a liability on both fronts?

That isn't accurate. The existence of the flyover made it easier to justify the cost but the existence of the flyover was not the key driver behind the business case. To think that it is was is worrying and suggests the benefits of the project have been missed despite the publicity.

BTW - The flyover was not going to fall on anyone!

Worse than expected in one particular area (the bearings) and the bridge decks would have had to be jacked up in pairs (twice per deck) to address hence very disruptive to the WCML undeneath.
Generally in quite good condition.

Indeed - it is less disruptive to train services to replace the sections. It is more disruptive to road users in Blethcley mind!
 

DelW

Established Member
Joined
15 Jan 2015
Messages
3,896
Have plans been drawn up for a new Bletchley Viaduct?
It's to be hoped they have, since the current demolition is in preparation for it!

It will be essentially a concrete box over the WCML tracks, with the existing outer spans of the old viaduct connected to it. I think there were some sketches earlier in the thread.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,946
Location
Nottingham
Re Bletchley viaduct- It could have been worse. It could have been a 'listed' structure needing to be kept for posterity- after all it was surely of historical interest having been closed so soon after opening- maybe a record? I don't know dates or comparotors- maybe a Forumite (like Bletchleyite maybe?) will advise? Has the Concrete Society not complained?
Although the original purpose it was built for never materialized, the flyover itself remained in occasional use, possibly right up until the track was removed for the current works, and it's probably still officially "open" now.
Have plans been drawn up for a new Bletchley Viaduct?
I would imagine replacement spans have been designed and are probably in manufacture.
Which is why I resisted referencing rods for their own backs, as as it's bars and generally someone else makes them.
Reading that just reinforced my view that people are getting too pre-stressed about this. In the aggregate it doesn't make much difference.
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
29,325
Location
Fenny Stratford
Around 60 years old, which is a fairly typical design life for an RC structure. Plenty of motorway bridges of that era have needed major repairs or replacement.
It's often the ancillaries which fail (e.g. bearings, expansion joints) which then cause adverse effects on the main structural elements.


i understand it is the bearings not the structure that is the issue here.
 
Status
Not open for further replies.

Top