I will try and provide a link and a accessible format later.
Here you go:
Project Details | |
OP Code | 154396, 171845, 171848 & 171849 |
Output Driver | Decarbonisation of traction on the Scottish Network |
Operating Route | Scotland |
Date | July 22 |
Sponsor | Alastair Holmes |
Output Driver Detail
Network Rail's Decarbonisation Action Plan for electrifying rail traction for passenger services by 2035 is a steadfast commitment of Scottish Government's Climate Change Plan and is important for carbon reduction commitments. Traction Power is a key component in the rolling programme, with the objective of removing diesel passenger trains from the Scottish rail network and enabling operation of EMUs or BEMUs.
Transport Scotland Required Outputs
Transport Scotland has remitted Network Rail to develop an electrified network that supports the Scottish Government's Climate Change Plan by providing additional electrical capacity on the rail network.
Scope of Works
The scope of the project is:
- The provision of four new Feeder Stations in the East of Scotland to support full electrification (enabling operation of Electric Multiple Units), or through partial electrification (enabling operation of Battery-Electric Multiple Units. At Currie and Portobello (where the existing feeder station will be decommissioned) the electrical capacity of the existing network will be increased, which supports additional electric passenger and freight services
- The four locations are: Thornton (171845), Portobello (171849), Tweedbank (171848) and Currie (154396)
Interfaces and Assumptions
- The project is a component part of the broader Rolling Programme of Decarbonisation
- The project supports Fife Phase 1, Levenmouth, Borders Decarbonisation and the Edinburgh area electrical capacity increase
Activities and Milestones (NR) | ||||
Milestone | Description | Aspirational Date | Status | |
Agree single option | Option selection completed | A | September 2021 | Achieved |
Approval in principle | Asset Manager accepts design | A | November 2021 | Achieved |
Contract Award | Contract signed and instructed | A | January 2022 | Achieved |
Portobello Feeder Station | National grid connection | A | November 2024 | On Schedule |
Thornton Feeder Station | National grid connection | A | November 2024 | On Schedule |
Tweedbank Feeder Station | National grid connection | A | June 2024 | On Schedule |
Currie Feeder Station | National grid connection | A | August 2023 | Revised |