LNW-GW Joint
Veteran Member
Difficult to tell.When laying the extension lead have they avoided the footprint of any Miles Platting re-alignment?
The cable route dives under the current curve roughly at its sharpest point.
Difficult to tell.When laying the extension lead have they avoided the footprint of any Miles Platting re-alignment?
Is Anneka Rice involved?7 miles of piles/foundations/ masts/SPS and wires in 3 days? Most unlikely!!
Is Anneka Rice involved?
Future-proofing. It also means that Manchester Victoria won't have to be closed for OLE works nearly as much.If the overheads don't go that far out of Victoria towards Miles Platting and it seems they won't be going any further for the foreseeable future then what was the point in putting them up in the first place as nothing is going to be able to use the wires surely?
Future-proofing. It also means that Manchester Victoria won't have to be closed for OLE works nearly as much.
My understanding was that it would allow trains to reverse at the crossovers to the East of Victoria. Thus meaning they did not block a platform at Victoria.If the overheads don't go that far out of Victoria towards Miles Platting and it seems they won't be going any further for the foreseeable future then what was the point in putting them up in the first place as nothing is going to be able to use the wires surely?
Indeed, that's also rather useful, alongside wiring the crossovers now so less time and money needs to be spent on them later.My understanding was that it would allow trains to reverse at the crossovers to the East of Victoria. Thus meaning they did not block a platform at Victoria.
And shunt into one of the east-facing bays if necessary.My understanding was that it would allow trains to reverse at the crossovers to the East of Victoria. Thus meaning they did not block a platform at Victoria.
It seems not at the moment.Are they thinking of connecting Newton Heath with 25kv?
Track foundation improvements between High Wycombe and Leighton Buzzard
Is there much use of the bays now? It's a while since I've been the "wrong" side of the Pennines but I was under the impression that pretty-much everything ran through these days.
Even after the May timetable change, there are still 2tph booked to reverse in Vic Platform 2:Is there much use of the bays now? It's a while since I've been the "wrong" side of the Pennines but I was under the impression that pretty-much everything ran through these days.
The overhead wires going up to miles platting are now live as well as platforms 1 and 2;
https://t.co/Ta3HB2eYQ2
Yes, not one of Network Rail's most accurate press releases. The wires only go as far as the Bromley Street area, well short of Miles Platting Junction. And there are not yet any wires into P1/2 to be energised!What's all this with wires to Miles Platting? I thought they were going to end a train length beyond the protecting signals so an EMU could shunt between platforms.
Electrification only going as far as Bromley Street Junction, which is only 29 chains from Manchester Victoria, so we are talking about 638 YARDS max. I think this is about the third time NR have announced the electrification being complete so far!!!What's all this with wires to Miles Platting? I thought they were going to end a train length beyond the protecting signals so an EMU could shunt between platforms.
I assume the both ways ladder shown towards the bottom is referred to as Bromley Street by some, though evidently not by the Sectional Appendix. Incidentally not sure where "October 2009" comes into it as the page shown is from 2019.
I don't really understand that. There's no Junction 29 chains from Victoria as far as I can see?? *scratches head*
See this article about Victoria East Junction, including some pictures showing the track diagram and giving some idea of what the layout used to be.The dotted metrolink lines are your subtle hint - what was it like pre MetroLink?...
Very obvious from google satellite view.
memory of the day I visited Manchester Victoria East Jcn., so many, many years ago ('64). They didn't have buttons there. They had bloody big switches lad, good, solid, Lancashire, by goom switches - yards (well feet anyway, perhaps a good 25 ft plus was the length of the panel?), triple and quadruple banked switches, which would have put those of another box’s Belling food warmer to shame! And even if they weren't ceramic, I wouldn't knock it! It was One Control Switch (OCS) lad, 'lectric (and damned proud of it they were too) which, at the time, was something out of a science fiction magazine to me. Built brand new in 1962 and only two years old, state-of-the-art, 1955 Modernisation plan stuff. And I was standing in front of it!
Fair enough, I don't have access to the live document, so that was the best I could do.That's an out-of-date Table A, Bromley Street Jn has been shown for a few weeks now in the live document.