Boots on the ground more likely 2024The disappointment is that the last line says it only goes out to tender September 2022. So no boots on the ground until early 2023 best I would assume.
ITT Sept 2022
Return Tenders Dec 2022
Evaluate til Feb 2023
Clarification til Apr 2023
Award June 2023
Mobilisation, design and materials procurement is likely to take till Dec 2023
However, this was supposed to be an oven ready scheme so work must have been in hand already South of Leicester to potentially get piling going in advance.
Answering the question of potential bidders
Also Network Rail will be canvassing for ideas on the most efficient delivery method to avoid cost overruns that dogged previous electrification projects.
You know the answer will be blockades and if acceptable how much lead time is needed from contract award to say mobilise to deliver Market Harborough to Leicester under that approach - 18 months? So could be at Leicester for Dec 2025 timetable change, 2026 Nottingham, 2027 Sheffield.
Whats happening with Kettering to Market Harborough - has it been awarded as an extension SPL?