edwin_m
Veteran Member
Does the presence or absence of ramps on the footbridge make any difference to that?The have been a lot of accidents at Attenborough crossing
Does the presence or absence of ramps on the footbridge make any difference to that?The have been a lot of accidents at Attenborough crossing
I was assuming this related to the foot crossing to the nature reserve that has a history of fatalitiesDoes the presence or absence of ramps on the footbridge make any difference to that?
Track the discussion back to #8027 and I believe we are discussing the road level crossing (with footbridge) at the station. The one in the nature reserve looks easier to replace, with ramps if necessary, though it would take a bit of land out of the reserve itself.I was assuming this related to the foot crossing to the nature reserve that has a history of fatalities
I think its to mark the planned location of the catenary poles.I have also now seen a peg! This solitary find was in the car park opposite Sileby station, looking up towards the down fast.
The peg was in a sort of ballast well, which might be hard to notice on the photo, but was dead obvious in reality. What does the process of ‘pegging’ the ballast entail?
That'll be the lookoutMML electrification related - here’s a pic from yesterday of some headspan upgrades near St Albans. I do hope that chap at bottom right is OK
View attachment 175685
I would hope both on the right are okMML electrification related - here’s a pic from yesterday of some headspan upgrades near St Albans. I do hope that chap at bottom right is OK
View attachment 175685
I expect he’s keeping that length of old rail from suddenly moving…That'll be the lookout.
Ah, what I meant was, how do they go about sticking the pegs in? What sort of plan / survey / digging are they doing for just these pegs?I think its to mark the planned location of the catenary poles.
Typically, a 1m^3 hole is dug to find out the type(s) of soil (and depths in that 1m hole thereof) in that given location.Ah, what I meant was, how do they go about sticking the pegs in? What sort of plan / survey / digging are they doing for just these pegs?
Wow. 1 cubic metre is a lot!Typically, a 1m^3 hole is dug to find out the type(s) of soil (and depths in that 1m hole thereof) in that given location.
I always assumed they would just take a soil sample with an augerWow. 1 cubic metre is a lot!
If you just plunged into the ground with an auger, you’d potentially end up with the same situation as during the GW electrification where signalling and power cables were damaged because their positions were unknown.I always assumed they would just take a soil sample with an auger
This authorisation is for the placing in service of, • UKMS 125 Overhead Contact Line System between Kettering North Junction (SPC3 72 M 0676 YDS) to Wigston South Junction (SPC3 95 M 0350 YDS).
Of course by the time the 810's are ready to use it NR will probably want it retestedThe ORR "Letter of Authorisation" for the Kettering to Wigston OLE has recently been posted on the ORR Website:
Interoperability authorisations | Office of Rail and Road
Details of all the new, major, upgraded or renewed infrastructure or rolling stock projects we have authorised into service under the Railways (Interoperability) Regulations 2011.www.orr.gov.uk
Just need the electric trains to go with it!
Some 810's are already (intermittently) out and about though, being tested, so they should be using the newly authorised section fairly regularly between now and when they eventually go into passenger service.Of course by the time the 810's are ready to use it NR will probably want it retested
Wow! I'd be grateful for an explanation of this postInteresting that Wigston is termed a MPATS. Does this mean that this will be the permanent northern boundary for Braybrooke ATFS, or just temporary until wiring to Syston, the putative southern boundary for the Kegworth (AT?)FS?
WAO
OLE upgrades south of Bedford are 60% complete and we're on track to complete the work this summer. Thank you for your patience. There will be disruption this weekend, please check before you travel.
Probable answer in bold since Wigston MPATS is accompanied by a neutral section.Interesting that Wigston is termed a MPATS. Does this mean that this will be the permanent northern boundary for Braybrooke ATFS, or just temporary until wiring to Syston, the putative southern boundary for the Kegworth (AT?)FS?
MPATS - Midpoint Autotransformer Site (midway between feeder stations; a boundary between traction supplies)Wow! I'd be grateful for an explanation of this post
Is there a neutral section at Braybrooke? Or in another terms, does it have 1 or 2 grid supplies.Here's a very brief update from NR on OLE125 progress:
Probable answer in bold since Wigston MPATS is accompanied by a neutral section.
MPATS - Midpoint Autotransformer Site (midway between feeder stations; a boundary between traction supplies)
ATFS - Autotransformer Feeder Station (entry point for traction supplies)
In a classically-fed system they would generally be labelled Midpoint Track Sectioning Cabin (MPTSC) and Feeder Station (FS) respectively.
Also, inclusion of the Napsbury / East Hyde sites within that authorisation letter is of mild curiosity to me since they've been fully operational for almost two years.
Braybrooke does indeed have a neutral section, and has 2 SGTs (Super Grid Transformers) from the 400kV circuit.Is there a neutral section at Braybrooke? Or in another terms, does it have 1 or 2 grid supplies.
It definitely has two complete grid side supply systems, fed off two grid circuits. They were connected separately, about a year apart, it was covered earlier in the thread, the grid circuits on the two sides of the pylons across the site are separate and can be switched independently.Is there a neutral section at Braybrooke? Or in another terms, does it have 1 or 2 grid supplies.
It definitely has two complete grid side supply systems, fed off two grid circuits. They were connected separately, about a year apart, it was covered earlier in the thread, the grid circuits on the two sides of the pylons across the site are separate and can be switched independently.
Thanks!!Braybrooke does indeed have a neutral section, and has 2 SGTs (Super Grid Transformers) from the 400kV circuit.
I was chatting to one of our other Instructors last week who is closer to the 810 project than I am currently, and he confirmed that the power changeover boards for Sharnbrook are not going to be installed, so ac operation from Wigston right through to Pancras. The boards already in place between Elstree Tunnel and Mill Hill will be redundant before they even came into use.I do agree that Class 810 passenger workings probably won't need to utilise the M1-adjacent changeover zone (i.e. operate pan-down on the country-side of Mill Hill Broadway) by the time they eventually cocommence.
Picture below shows installation of new overhead wire equipment.