• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

MML Electrification: progress updates

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
32,840
Adjacent to a new housing development just south of Bedford, I’ve noticed a row of new OLE portals being installed.

These are set back further away from the running lines compared to the existing headspans. Is there going to be a loop installed here?
Is it for track realignment around Wixams Station platforms?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,854
Yes. Plan is for the up slow to be realigned and two platforms (one for each of the slows only) installed either side of it.

However - a proposed Universal Studios theme park in that area, if greenlit, would come with a more comprehensive infrastructure package (including a bigger station); the current Wixams scheme would be terminated as a consequence. There are more details on the threads linked below:

 

LTJ87

Member
Joined
1 Jun 2008
Messages
152
Network Rail has put out a press release ahead of this weekend’s closures, stating there should be limited disruption on the south end of the MML for the rest of the year once works are complete in early June.


Once this work is complete in early June, there will be limited disruption on the southern stretch of the Midland Main Line until Christmas 2025.

Meanwhile, major strides continue to be made in the Midland Main Line overhead line OLE125 project, allowing bi-mode trains to travel at up to 125mph between London and Bedford. Work to upgrade the track and overhead power lines is almost two-thirds done – and remains on track for completion this summer.
 

Smoggy

Member
Joined
4 Aug 2009
Messages
84
Thanks!!
This means, however, that Braybrook A feeds about 25 miles of line to Sharnbrook, while Braybrook B only supplies around 13 miles to South Wigston. Does this mean Braybrook B is expected to supply through South Wigston in some N-1 situations (I know that normally Mid Point substations are only bypassed in N-2 times) - or is it likely all down to where the 400kV connections were available. It is a somewhat notable mismatch especially when fewer electric trains will be on the northern side of the feeder station.
Braybrooke SGT2/F2 will only normally feed Braybrooke to Wigston MPATS, but has the ability to feed further in both dirrctions. We have recently had F2 feeding both ways so feeding Sharnbrook to Wigston.

Likewise if there are any planned Isolations between Kettering and Braybrooke, then Long Meadow Farm ATFS F2 will feed through Sharnbrook all way to Corby.
 
Joined
5 Aug 2015
Messages
197
Location
Norfolk
Braybrooke SGT2/F2 will only normally feed Braybrooke to Wigston MPATS, but has the ability to feed further in both dirrctions. We have recently had F2 feeding both ways so feeding Sharnbrook to Wigston.

Likewise if there are any planned Isolations between Kettering and Braybrooke, then Long Meadow Farm ATFS F2 will feed through Sharnbrook all way to Corby.
Those are some quite long feeding distances!
Which makes me ask: what parts of MML are feeding in AT mode at the moment?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
32,058
Kinda surprised that the bedford-corby project didnt install AT equipment. Where/what are the other substations north of Bedford?

Dont forget that the power draw north of Luton is (and will be) relatively low compared to south of Luton.
 
Joined
5 Aug 2015
Messages
197
Location
Norfolk
Dont forget that the power draw north of Luton is (and will be) relatively low compared to south of Luton.
Even with the 125mph intercity services?

Did some looking around of my own, seems like AT was descoped at some point. Does this mean they were hoping for electric freight which is now less of a possibility?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
32,058
Even with the 125mph intercity services?

Yes. Speed is irrelevant, it is power draw that matters. 4 x intercities an hour + 2 x EMUs is quite a light load. Bear in mind that the entirety of the ECML and WCML didnt‘t have AT until recently, and even now only parts do.


Does this mean they were hoping for electric freight which is now less of a possibility?

It’s more of a possibility now than it has been for a long time!
 
Joined
5 Aug 2015
Messages
197
Location
Norfolk
Yes. Speed is irrelevant, it is power draw that matters. 4 x intercities an hour + 2 x EMUs is quite a light load
.
So why was AT originally specified? Just for the longer feedind distances for each FS?
Bear in mind that the entirety of the ECML and WCML didnt‘t have AT until recently, and even now only parts do.
Is there actually any AT on ECML? Seen conflicting info on this
 

InTheEastMids

Member
Joined
31 Jan 2016
Messages
967
Yes. Speed is irrelevant, it is power draw that matters. 4 x intercities an hour + 2 x EMUs is quite a light load. Bear in mind that the entirety of the ECML and WCML didnt‘t have AT until recently, and even now only parts do.
Does this mean that the next feeder station at Kegworth is strictly necessary for the Wigston-Trent bit of MMLE (assuming there will not now be a gap from Wigston to Syston)?

I'm thinking of how the Corby electrics started before Braybrooke was commissioned. At this rate, the only demand will be the 4tph EMR IC (which can switch to diesel if there's maintenance to be done).
 
Joined
5 Aug 2015
Messages
197
Location
Norfolk
Does this mean that the next feeder station at Kegworth is strictly necessary for the Wigston-Trent bit of MMLE (assuming there will not now be a gap from Wigston to Syston)?

I'm thinking of how the Corby electrics started before Braybrooke was commissioned. At this rate, the only demand will be the 4tph EMR IC (which can switch to diesel if there's maintenance to be done).
I assume you mean *isn't strictly necessary*.

And yeah, as mentioned in #8,078. Braybrook in general has a decent amount of spare capacity.

In particular, the feeding distance northwards is quite a way shorter than southwards. If I'm using the nomenclature correctly, SGT1 and Feed 1 supply ~25miles southwards to Sharnbrook as well as the stretch to Corby. SGT2 and Feed 2 feed just the two track line northwards to South Wigston (13 miles). As is standard practice, both transformers are equal and designed to handle the entire range from South Wigston to Corby/Sharnbrook (so that one outage doesn't affect the service).

So I'd absolutely imagine Braybrooke could feed through Wigston on a regular basis if Leicester to Syston gets wired before Syston to Trent jncs
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,364
It’s more of a possibility now than it has been for a long time!
How? Unless it comes with Bi-mode locomotives there surely still won't be much as the MML isn't linked to anywhere else electrically as far as Freight Trains are concerned as far as I am aware.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,715
Location
Between Beeston (Notts) & Bedlington
So why was AT originally specified? Just for the longer feedind distances for each FS?

Is there actually any AT on ECML? Seen conflicting info on this
There is, but only between Welwyn & Hitchin (and mainly fed from Corey's Mill (between Stev'age & Hitchin); even then it's not at full capacity).

Yep, you said it…
And, sadly, there seems to be no great hurry to wire either the Dudding Hill Line (although the West London Orbital (or whatever moniker Sir Sadiq (or his successor) bestows upon it) might change that) or the Carlton Rd Jn - Junction Rd Jn line.

Yes. Plan is for the up slow to be realigned and two platforms (one for each of the slows only) installed either side of it.

However - a proposed Universal Studios theme park in that area, if greenlit, would come with a more comprehensive infrastructure package (including a bigger station); the current Wixams scheme would be terminated as a consequence. There are more details on the threads linked below:

On a similar note, more new structures have popped up just north of the M25 underbridge, presumably for the tie-in to the new Radlett SRFI.
 
Last edited:

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
32,058
And, sadly, there seems to be no great hurry to wire either the Dudding Hill Line (although the West London Orbital (or whatever moniker Sir Sadiq (or his successor) bestows upon it) might change that) or the Carlton Rd Jn - Junction Rd Jn line.

Both are tricky electrification jobs, particularly the latter. But 99s will be perfect for them, given their distance and speed.
 

InTheEastMids

Member
Joined
31 Jan 2016
Messages
967
Both are tricky electrification jobs, particularly the latter. But 99s will be perfect for them, given their distance and speed.

I was thinking along the same lines about how the 99s might be perfect for aggregates traffic, and you've got there first.

What I was thinking (and may help people less familiar with the MML, or spur further debate):
For example, Bardon - MML is downhill and basically walking pace, so it can't need much power.
Then onto electric where you'd hope to see a significant performance benefit on the climbs out of the Soar/Welland/Nene/Ouse valleys
Back onto diesel for the Dudding Hill line (slow), and a crawl through South/West London behind stopping services to a final destination like Angerstein Wharf.

There's basically no heavy freight south from Leicester in the daytime, and I am guessing this is because they cannot get to Kettering without holding up an IC. So they run overnight, or go via Melton/Corby (if originating at Mountsorrell or further North).

If a class 99 has enough oomph to go via Harborough without delaying EMR, then doing so saves mileage, time and releases a bit of capacity between Syston and Manton Junction
Coming back the other way, it's all empties so clearly power is less of an issue (there's Northbound freight trains even during the peak periods).
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,854
There is, but only between Welwyn & Hitchin (and mainly fed from Corey's Mill (between Stev'age & Hitchin); even then it's not at full capacity).
I've travelled on that stretch somewhat recently and not seen any ATF wires, so I'm pretty sure it's boosterless classic like much of the ECML. Welwyn North - Knebworth aside it wouldn't need to be insulated either.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,715
Location
Between Beeston (Notts) & Bedlington
I've travelled on that stretch somewhat recently and not seen any ATF wires, so I'm pretty sure it's boosterless classic like much of the ECML. Welwyn North - Knebworth aside it wouldn't need to be insulated either.
The ATF is all cabled on that stretch. Some time ago, I was fortunate enough to talk with someone involved on ECPSU Phase 1 and he stated that the cabled ATF throughout was used because of the track layout.
On the GWML, MML & WCML (including the Trent Valley section), 1 pair of lines can be closed while the other pair remains open. Similarly, the OLE over those lines and 1 of the 2 ATFs could be isolated to allow work to be undertaken.
GWML:
|DM||UM||DR||UR|

MML/WCML (except Trent Valley):
|DF||UF||DS||US|

WCML (Trent Valley):
|DS||DF||UF||US| - Fast lines are, however, bi-directional

ECML:
|DS||DF||UF||US| - no bi-directional working

With the ECML's track configuration being the way it is, maintenance of the aerial ATF would require more frequent all-line closures.
A side note - as far as I know, the ATs at Welwyn, Langley Junction & Hitchin are operational, but the ones at Corey's Mill are not.
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,854
The ATF is all cabled on that stretch. Some time ago, I was fortunate enough to talk with someone involved on ECPSU Phase 1 and he stated that the cabled ATF throughout was used because of the track layout.
On the GWML, MML & WCML (including the Trent Valley section), 1 pair of lines can be closed while the other pair remains open. Similarly, the OLE over those lines and 1 of the 2 ATFs could be isolated to allow work to be undertaken.
GWML:
|DM||UM||DR||UR|

MML/WCML (except Trent Valley):
|DF||UF||DS||US|

WCML (Trent Valley):
|DS||DF||UF||US| - Fast lines are, however, bi-directional

ECML:
|DS||DF||UF||US| - no bi-directional working

With the ECML's track configuration being the way it is, maintenance of the aerial ATF would require more frequent all-line closures.
A side note - as far as I know, the ATs at Welwyn, Langley Junction & Hitchin are operational, but the ones at Corey's Mill are not.
Well, that is most enlightening. I suppose the requirement for insulated ATFs throughout (at least on 4-track paired-by-direction sections) was a factor in ECPSU "only" getting the line deboostered elsewhere.

Back on the MML (specifically between the M25 and Radlett SRFI underbridges) I've noticed one of the portals supports spanwire-linked cantilevers identical to those in Mk3 headspans. I know previous installations are common on bridges/viaducts but the lack of mechanically independent registrations is not something I'd have associated with a new portal these days.
 

Top