Here is a glimpse of some of the issues...
Work needed for restoration of signalling at Caldew, if all goes well and timescales are met without further problems !
Build 6 new location cabinets & deliver to Carlisle depot.
Test/renew lineside cable/equipment and refurbish 8 existing location cabinets. to be Completed by 1600 Friday 11/12.
Pre-test all 6 new location cabinets at Carlisle depot. Completed by 1800 Saturday 12/12.
Erect the 6 new location cabinets at Caldew. 12 hour possession Sat/Sun.to be Completed by 1800 Sunday 13/12.
Connect up cables to the 6 new location cabinets & test all cabling. Sunday. to be completed by 1800 Sunday 13/12).
Connect & test power supplies throughout 3 x 12 hour TBW daytime working required between Monday 14/12 & Thursday 17/12.
Install & setup transformers.
Through test 90+ circuits.
Fully test 7 track circuits.
Full correspondence test of all points 1 x 6 hour block required on Friday 18/12.
Correspondence & aspects sequence testing & commissioning. 12 hour block Sat/Sun 19/20.
Full signalling functionality returned at Caldew. 1100 Sunday 20/12.
Wow ! All the best with that, and I hope the weather doesn't intervene !