• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Stevenage platform 5

Status
Not open for further replies.

Hadders

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
27 Apr 2011
Messages
13,202
I suspect the gateline will be left open most of the time. Maybe they’ll man it for a few minutes before departure - there’s only going to be 2 trains an hour from that platform.

Also anyone catching a train from that platform is likely to encounter a barrier at the other end of their journey.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Failed Unit

Established Member
Joined
26 Jan 2009
Messages
8,881
Location
Central Belt
I suspect the gateline will be left open most of the time. Maybe they’ll man it for a few minutes before departure - there’s only going to be 2 trains an hour from that platform.

Also anyone catching a train from that platform is likely to encounter a barrier at the other end of their journey.

Really, we have a lot of stations without barriers on the WGC side.
 

Hadders

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
27 Apr 2011
Messages
13,202
Really, we have a lot of stations without barriers on the WGC side.

Platform 5 won’t serve the WGC side, only the Hertford loop side. Yes, there are unbarriered stations but the main destinations like Hertford North and Enfield Chase do have barriers. I suspect it will cost far more to man the barriers permanently than staff them continuously.
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
28,058
Location
UK
The layout is clearly a mess but will be addressed if and when the entire station (if not half of Stevenage) is rebuilt with the grand plans from the council. Eventually you'd have a single station, presumably with just one gateline, and lifts within the protected area. Consider this a temporary solution and I'm sure the design has been based around whatever plans are in place for a rebuild.

Extending contactless acceptance to Stevenage would almost certainly see it being added to all the other stations south. Obviously Watton-at-Stone but also Knebworth and Stevenage. This would presumably be up to TfL.

As for revenue protection, there are many stations that have no gates and infrequent blocks, so if you aren't protecting the small stations then you need to have near constant protection of the main places where these people are going to/from. Short faring then becomes an issue, but at least you've got some money that way.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,439

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,495
Location
Between Peterborough & Bedlington
T3 possession on the Down Slow from Woolmer Green to south of Hitchin, and on the northbound Hertford Loop track at Langley Jn today. Track replacement might have been going on; a Kirow crane (one of Balfour's) was on site.
 

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
T3 possession on the Down Slow from Woolmer Green to south of Hitchin, and on the northbound Hertford Loop track at Langley Jn today. Track replacement might have been going on; a Kirow crane (one of Balfour's) was on site.

And it’s just a coincidence that they’ve had OHL problems in the Knebworth area earlier today too....
 

Skimpot flyer

Established Member
Joined
16 Nov 2012
Messages
1,613
View of the works, taken yesterday from the staircase that connects the station footbridge to the leisure park...
CE3C8517-CC71-4F5B-B9FE-00D5FEC16F50.jpeg
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
Well that was interesting. They haven't installed the switch...... They have simply replaced around 300m or so of track on the Hertford Loop starting at the switch where the loop joins the down slow. I was informed by one of the chaps working on site that the switch is going in next weekend as planned. However he did say that if they had been given possession earlier then the point would have been installed.

I've lots of footage to edit, and will be back down there tomorrow for a couple of hours to see the rest of the work (looks like ballast and tampers are backed up in the loop awaiting entry)

@Skimpot flyer - excellent image, you clearly get a feel for how the platform will look
 

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
Thanks guys for the photos, it's good to see Platform 5 coming along nicely!

Question though, what will the line be called? Up/Down Stevenage? Up/Down Hertford? Also any idea when we can expect the track to be in place and the OHL being installed?
 

Skimpot flyer

Established Member
Joined
16 Nov 2012
Messages
1,613
@Skimpot flyer[/USER] - excellent image, you clearly get a feel for how the platform will look

Thanks. I was surprised at the progress made and to see ballast and some track is already in place. Was I correct in thinking that passive provision is being made for the new line to operate as a through line, in future?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,439
Thanks. I was surprised at the progress made and to see ballast and some track is already in place. Was I correct in thinking that passive provision is being made for the new line to operate as a through line, in future?
It’s mentioned in the planning environmental statement (ES) that the chosen option allows for extension northward if more platform length is required, ie beyond the provided 6 car. The current platform and stairs position means no alterations are needed to the existing footbridge and ramps, which are local authority owned. The ES doesn’t explicitly mention the possibility of connecting the platform 5 track back into the down slow beyond a future platform. It’s possible it’s been considered but not described.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
. Was I correct in thinking that passive provision is being made for the new line to operate as a through line, in future?

Not 100% sure I know what you are referring to as the turnback will be a terminus platform, so won't be a through line in that sense. But at the langley end the connection to the main line will remain, with the new switch being installed (fingers crossed) next week transforming the junction into a cross-over.

Your photo stunned me too - my wife had to use the train from stevenage last week and took some pictures and it wasn't as advanced as it looks in your image. My personal feeling is that with the point installed next week, the bulk of the track bed will then be installed once they stop using the section between six hills way and mid-point between six hills and A602 bridges as the roadway for trucks etc, probably working back from Langley junction towards the station. This would then leave the station building to be completed, with easy access from the leisure park. - Just
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
It’s mentioned in the planning environmental statement (ES) that the chosen option allows for extension northward if more platform length is required, ie beyond the provided 6 car. The current platform and stairs position means no alterations are needed to the existing footbridge and ramps, which are local authority owned. The ES doesn’t explicitly mention the possibility of connecting the platform 5 track back into the down slow beyond a future platform. It’s possible it’s been considered but not described.

I think that any further development may be part of proposed plans to revamp the complete station as part of the new town development plan....can't see it happening any time soon though
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,439
I think that any further development may be part of proposed plans to revamp the complete station as part of the new town development plan....can't see it happening any time soon though
Yes that does get mentioned in passing, as justification for building everything to do with the new P5 south of the footbridge, ie leaving anything more disruptive to a bigger revamp.

(The planning ref and Stevenage website link is in post #162, if anyone is wondering.)
 

Hadders

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
27 Apr 2011
Messages
13,202
Thanks. I was surprised at the progress made and to see ballast and some track is already in place. Was I correct in thinking that passive provision is being made for the new line to operate as a through line, in future?

I believe there is passive provision for it to become a through line in the future.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,398
Well that was interesting. They haven't installed the switch...... They have simply replaced around 300m or so of track on the Hertford Loop starting at the switch where the loop joins the down slow. I was informed by one of the chaps working on site that the switch is going in next weekend as planned. However he did say that if they had been given possession earlier then the point would have been installed.

I've lots of footage to edit, and will be back down there tomorrow for a couple of hours to see the rest of the work (looks like ballast and tampers are backed up in the loop awaiting entry)

@Skimpot flyer - excellent image, you clearly get a feel for how the platform will look

Removing the old ballast, installing the matting between sub-base and installing new ballast and levelling before any new track goes down takes quite a bit of time hence well worth getting that all out of the way on the entire stretch being relaid (& slightly realigned) - the points are and easy separate job for late then.

PS -I noticed in the video there are 4 track panels for the points and the existing Hertford Loop to DS point look like timber sleepers - are they changing the existing set as well as installing new, if so an even better reason to leve the point for another weekend.
 
Last edited:

malc-c

Member
Joined
1 Dec 2017
Messages
990
Removing the old ballast, installing the matting between sub-base and installing new ballast and levelling before any new track goes down takes quite a bit of time hence well worth getting that all out of the way on the entire stretch being relaid (& slightly realigned) - the points are and easy separate job for late then.

PS -I noticed in the video there are 4 track panels for the points and the existing Hertford Loop to DS point look like timber sleepers - are they changing the existing set as well as installing new, if so an even better reason to leve the point for another weekend.

It could well be part of the plan to replace the existing switch at the same time seeing that all other point work for the junction has been upgraded. I guess we'll just have to wait until next weekend to see exactly what gets installed.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,398
It could well be part of the plan to replace the existing switch at the same time seeing that all other point work for the junction has been upgraded. I guess we'll just have to wait until next weekend to see exactly what gets installed.
All the panels (at least 5) are visible at ~9 and 21-22minutes in the video but I can't see what all off them are!
 
Status
Not open for further replies.

Top