Moving off the subject of Network Rail's ownership, and on to the actual subject of the thread...
Makes for a good read, fascinating to see that they didn't report it themselves too, hmm!
Cheers OT!
Thank you for your observations.
What is set out in the Report is the attitudes and behaviours that Network Rail maintenance people have been displaying for some time, and which are familiar to those who have to work with them.
This is not the first time such attitudes have been suspected by RAIB, but this particular Report is the first time where they have been flushed out and there is demonstrable and irrefutable evidence.
Any renewals man on here can regale you with tales of how Maitenance have waltzed into Possessions and Possession planning meetings demanding access where others would have been denied, and causing disruption to carefully planned and programmed works which have been in the pipeline for many months.
A common one is the late tamping site. Although tampers are at a premium, and are programmed for months out, Maintenance appear to be completely unable to plan more than a week out and thus will arrive at a Possession meeting with a need to find a site to tamp. If it just happens that this is in someone else's worksite then tough, and if it falls between two worksites, they will be combined and possibly reduced, leaving some poor sod without a worksite for their planned work.
On other occasions, they do not even bother to turn up at the meeting but simply organise it with the PICOP. By way of example, one Saturday night we were on a 7-day weld defect site. A tamper was spotted warming up and enquiries made because there had been no mention of any tamping taking place. It turned out to be a tamper allocated for maintenance that they did not even know they had booked until a day or two before.
We were then told that the tamper would enter our worksite and do some tamping before going off elsewhere. It was made quite clear to us that WE must accomodate this activity despite it not being discussed or agreed with us. Our ES naturally reported the incident and I reported it in as an "incident" in accordance with our Procedures. The point being that what was being proposed was contrary to Network Rail's own planning and Possession procedures.
Our protestations about the need to remove the weld defect came to nothing until we took the decision to withdraw from the job, notifying the PICOP that as we now had insufficient time to remove the defect, we would be holding the worksite until the line was available to us to carry out the weld repair, which would incur a considerable over-run as our people would be taking the appropriate rest time before returning.
There then followed a long series of phone calls with increasingly senior individuals who all considered that a 7-day defect was only so until THEY decided it wasn't. None of course were prepared to issue a written instruction to that effect (because legally they couldn't) but they tried to bully the team into handing back with the 7-day weld left in situ beyond that date. Now a 7-day defect is called that for precisely that reason, it can only stay in for 7 days.
The standoff eventually ended with us completing the work and the Posession over-running. The Monday morning Inquest however would only address OUR having failed to complete in the booked time. It did not and would not address the true reasons, nor would it investigate the issue of bullying behaviour. Our incident report was buried through the medium of threats being made about the Company being taken off the Contract - simply for following declared Network Rail reporting processes.
Any Renewals man worth their salt will have identified a number of other iregularities on the site in the Report that have obviously taken place that are not discussed, and it is noticable that the man's "manager" either did not know or if he did know, chose to ignore the most obvious of all Rule Book and RRM machinery operations basics. How can you manage a man who seemingly knows more than you do ???
The labouring staff who came from an agency would certainly not report an issue as they would be marked up "NWB" (Not Wanted Back), and the agency would not have the slightest interest in causing any ripples that could upset its client.
This raises yet another issue with the use of cheap labour agencies against the bigger Infrastructure Contractors. The reason ? Safety and safety culture costs money. A major Infrastructure Contractor's supervisor would not have allowed the job to go ahead on safety grounds. THAT is why those Comapnies are now out of favour - that and the fact that properly trained and motivated staff cost money. Many of the major players staff are unionised against labour agencies who are not yet the Unions seem to find it acceptable to put its own trained members on the dole rather than unskilled non-union workers - work that one out ???
The shame is that the RMT continues to turn a blind eye to all of this because they were responsible for the creation of ths monster, and for Political dogma reasons they will not now accept that they were wrong. Meanwhile prepare to read more of this type of incident as Network Rail is starting to do more and more renewals in-house.
So far their attempts have raised a laugh in the Infrastructure world but now its going beyond that with things like this.