WatcherZero
Established Member
- Joined
- 25 Feb 2010
- Messages
- 10,272
Heard the trams are being given the provisional class number of 399/0
Heard the trams are being given the provisional class number of 399/0
Transport Acts
The Transport and Works Act 1992
The Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006
The Network Rail (Tinsley Chord) Order
NOTICE OF APPLICATION FOR AN ORDER
Network Rail Infrastructure Limited (Network Rail) of 1 Eversholt Street, London NW1 2DN and South Yorkshire Passenger Transport Executive (SYPTE) of 11 Broad Street West, Sheffield, South Yorkshire S1 2BQ are applying to the Secretary of State for Transport under section 6 of the Transport and Works Act 1992 for the above-mentioned Order under section 1 of that Act.
The Order would authorise Network Rail and SYPTE to construct and operate a short section of tramway and ancillary works at Tinsley, in the City of Sheffield, forming an extension of the South Yorkshire Supertram system to connect the Supertram and Network Rail networks on which tram trains may operate.
The Secretary of State has determined that the application is not to be made subject to an environmental impact assessment.
The application contains a statement that a direction for deemed planning permission is being applied for.
A copy of the application for the Order, and of all plans and other documents submitted with it may be inspected free of charge from 13 March 2015 to 28 April 2015 at the places and at the times set out in the Schedule to this notice.
A copy of the application for the Order, and of all plans and other documents submitted with it, may also be viewed at www.networkrail.co.uk/improvements/tinsley-chord/
A copy of the application for the Order, and of all plans and other documents submitted with it, may also be viewed at http://www.networkrail.co.uk/improve...tinsley-chord/
Out of interest, what time period has elapsed since the first official notification of this project and the official notification shown above?
The notice I linked was published on Friday and indicated that the formal application for an order had been received by the DfT. I suppose whether you count anything before that as official depends on what you mean by official.Out of interest, what time period has elapsed since the first official notification of this project and the official notification shown above?
I'm aware the new trams are dual voltage - is the whole route to Parkgate to be 750v DC initially?
Update from the Nottingham conference is opening predicted in early 2017. General disgruntlement from most. First vehicle is now complete in Valencia but not arriving in UK until November.
Network Rails head of the delayed £60m tram-train pilot between Sheffield and Rotherham has admitted that design problems have affected the pace of work and the infrastructure picture isnt positive.
Speaking at a panel session at the UK Light Rail Conference in Nottingham yesterday, Simon Coulthard (pictured) said his team is learning lessons the hard way but that design and implementation works should be complete by about autumn next year.
The original announcement said the project will see tram-trains operating between the cities of Rotherham and Sheffield from 2015, but this has been pushed to early 2017.
There are a lot of reasons why it has taken us longer to do the design. It is true that we are learning lessons the hard way, said Coulthard. I still dont quite understand why weve had three goes at traction power modelling and each time the model was giving us different answers about what the design of the traction power system should be.
One positive note for the project is that the first unit is now complete and is going through testing in Valencia it will arrive in the UK in November. The second unit is now in production and will be delivered in early 2016, and then the five other vehicles will be delivered throughout next year.
It is a wonder that a certain Mr A Shooter has not got his hands on the remaining examples of Blackpool Transport old-style single-decker trams and announced that he can produce tram-trains at a third of the cost using old tram bodies..:roll:
Certain people have proposed that for the T68s that were withdrawn from Metrolink.
This may seem a strange question but are the trams going to have their own dedicated platform at Rotherham Central given that the Supertram cars have much lower platform heights than National Rail platforms.
As I understand it, a low section of platform will be provided beyond the length usually used by heavy rail services.
That is correct - only Rotherham station needs platform extension, because the terminus at Parkgate is new and the Tramtrain runs through the existing platform at Meadowhall South
Another reason this project is far more sensible than the insane "diesel trams to Huddersfield" idea!
Whilst I like the idea of tram-trains, some local authorities are grasping at the idea seeing them as a new "pacer" for local services. Barnsley to Doncaster being one such idea being touted... My view remains, if your running mostly on street or on a tight urban alignment trams are best, tram-trains are great way of cheaply extending tram routes onto short sections of existing heavy rail routes - but if you want to run a rail service between two towns, stick to heavy rail, because light rail doesn't like speeds above 45-50mph - Metrolink to Sale being a prime example of high speed waggle