I found a YouTube channel with four driver training videos for the current resignalling between Ravensthorpe and Cottingley. Also shows new speed limits and station upgrades.

 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,034
Location
Mold, Clwyd
Impressive video.
Still a number of arched masonry bridges to worry about for the wiring project.

Does anybody know the logic behind the signal numbers - eg SL 4871?
Is there a route code in the number somewhere, or a location reference?
I'm presuming the SL prefix means Stalybridge-Leeds.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,057
Location
Bristol
Does anybody know the logic behind the signal numbers - eg SL 4871?
Is there a route code in the number somewhere, or a location reference?
I'm presuming the SL prefix means StStalybridge-Leeds.
The prefix indicates the control area (usually) so Stalybridge to Leeds is a good guess.
The number being odd/even indicates direction (can't remember which is up and down).
The first digit (sometimes first two) usually indicate line or pairs of lines, and may indicate wrong-direction or bi-di functions.
The last two or three digits are a (supposedly) unique ID within that control area.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,715
Location
Between Beeston (Notts) & Bedlington
Impressive video.
Still a number of arched masonry bridges to worry about for the wiring project.

Does anybody know the logic behind the signal numbers - eg SL 4871?
Is there a route code in the number somewhere, or a location reference?
I'm presuming the SL prefix means Stalybridge-Leeds.
SL could of course be Standedge - Leeds.

Related to this, I travelled on the route via Standedge yesterday (and will do so again tomorrow); new precast concrete signal bases are popping up at various points lineside between Hudds and Diggle, so including Standedge Tunnel in its entirety. New hardstanding areas (aka "suites") for Location Cabinets (LOCs) are being built along this stretch too, as well as between Ravensthorpe and Leeds.

(I counted 4 LOC suites under construction on the Up side between Slathwaite and Huddersfield, and 5 precast concrete signal bases, 1 of which was in the wideway. There were 2 LOC suites each under construction on the Up side between Slaithwaite and Marsden, between Marsden and Standedge Tunnel, and between Standedge and Diggle Jn.)
 
Last edited:

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
SL could of course be Standedge - Leeds.

Related to this, I travelled on the route via Standedge yesterday (and will do so again tomorrow); new precast concrete signal bases are popping up at various points lineside between Hudds and Diggle, so including Standedge Tunnel in its entirety. New hardstanding areas for Location Cabinets (LOCs) are being built along this stretch too, as well as between Ravensthorpe and Leeds.
I think (but I'm not certain) the S stands for Stalybridge- AIUI that's the boundary between the workstations (one in York ROC, the other in Manchester).

I found a YouTube channel with four driver training videos for the current resignalling between Ravensthorpe and Cottingley. Also shows new speed limits and station upgrades.

Good video, that. Surprised that the new bridge at Batley is where it's depicted though (assuming the CGI is accurate), almost on the footprint of the current subway. I'd have thought it'd be closer to the Leeds end of the station, as building the foundations for the steps on top of where the current steps to the footbridge are would presumably be trickier to build. Though disclaimer, I'm no structural engineer.

Would also mean a longer closure, as the subway can't stay in use while the bridge is under construction. Although if the work coincides with the Mirfield/Ravensthorpe blockade it won't matter, as the Up platform won't be in use and the Dewsbury shuttles will use the Down line in both directions.
 
Last edited:

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,330
Location
Rochdale
There's a few posts on the SL, yes Stalybridge to Leeds as the signals are plated for the route now rather than boxes. The boundary between Manchester and York ROC is just west of the current west end of Diggle Loop which goes into York ROC Huddersfield workstation :)
 
Last edited:

stibz

Member
Joined
7 May 2014
Messages
72
https://www.flickr.com/photos/rob_transpennine_upgrade/ and https://www.flickr.com/groups/14856999@N21/pool/ are good indicators of work going on between Hudds and Dewsbury.
The former Tilcon sidings at Dewsbury (w3w: https://w3w.co/silent.bunny.update) have been turned into a arrival/departure base for goods by rail for use on TRU W3.
"Mirfield Shed Bridge" (aka MVN2-191 "Woodend Road Overbridge", near Lower Hopton Football Ground) has also been demolished.
Yes that is me taking a lot of photo's around Dewsbury, Ravensthorpe & Mirfield, As it was and as it changes, they we can look back in future., While the line was shut last Sunday, I went to Mirfield station, engineers train being loaded with old ballast from where the old 4th track used to be in the past, then they put a membrane down and covered with new ballast. I asked when they where doing more, guy said not till week 40, plus laying new track a xmas he said. We'll see eh. Work on new bridge at Ravensthorpe near years end too. Oh forgot to say, they are boring test holes to check the ground state, where the line crossed the River Calder at Dewsbury, heading towards Ravensthorpe. Told its going to be called Baker Viaduct, crossing river & canal there, beside the old cast iron girder bridge.
 
Last edited:

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,330
Location
Rochdale
Just to marry up to Stibz photos and descriptions here's what I have saved as the final layout.

Track diagram HUD.jpg
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,094
Location
Lancashire
Quite stunning progress with OLE equipment Stalybridge to Guide Bridge. I'd estimate 80% installed, including the Portals seemingly running the full length of Dukinfield viaduct(s). One portal is erected over Ashton Viaduct.

One full wire run on both lines from just after Stalybridge West Jn in place and terminates just before Ashton Viaduct.

OLE structures over the Glossop lines at Guide Bridge West Jn, ready to take over supporting the wires.

One massive long portal, over both Huddersfield lines and the full width of the Sidings on the Up Side at Guide Bridge. That one is strange, I very much doubt the Sidings will be wired.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
Just to marry up to Stibz photos and descriptions here's what I have saved as the final layout.

View attachment 138674
Still think the arrangement of the fast/slow down lines at Huddersfield is a mistake. Hopefully common sense will prevail and it'll go back to the original plan.

One massive long portal, over both Huddersfield lines and the full width of the Sidings on the Up Side at Guide Bridge. That one is strange, I very much doubt the Sidings will be wired.
Presumably there wasn't space for a support between the running lines and sidings without compromising the loading gauge on one or both?
 

jonesy3001

On Moderation
Joined
13 Jul 2009
Messages
3,317
Location
Otley, West Yorkshire
Quite stunning progress with OLE equipment Stalybridge to Guide Bridge. I'd estimate 80% installed, including the Portals seemingly running the full length of Dukinfield viaduct(s). One portal is erected over Ashton Viaduct.

One full wire run on both lines from just after Stalybridge West Jn in place and terminates just before Ashton Viaduct.

OLE structures over the Glossop lines at Guide Bridge West Jn, ready to take over supporting the wires.

One massive long portal, over both Huddersfield lines and the full width of the Sidings on the Up Side at Guide Bridge. That one is strange, I very much doubt the Sidings will be wired.
I take it the 2 Sundays in August 6th and 13th is when they'll finish doing the rest of the wires and gantries?
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,087
Still think the arrangement of the fast/slow down lines at Huddersfield is a mistake. Hopefully common sense will prevail and it'll go back to the original plan.


Presumably there wasn't space for a support between the running lines and sidings without compromising the loading gauge on one or both?
Sorry remind me, what was the original plan? I also look at the Huddersfield layout and don't quite get the logic.

I assume what is now P4 is purely for Manchester stoppers? And the new island platform will handle all slow line trains terminating from Deighton direction.
 

John R

Established Member
Joined
1 Jul 2013
Messages
4,510
Still think the arrangement of the fast/slow down lines at Huddersfield is a mistake. Hopefully common sense will prevail and it'll go back to the original plan.
Given they have Transport & Works Act approval, I think that’s highly unlikely.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,404
Still think the arrangement of the fast/slow down lines at Huddersfield is a mistake. Hopefully common sense will prevail and it'll go back to the original plan.
Why? Given the need for slow trains to cross with fast eastbound trains, doing it in a platform seems a sensible choice. What am I missing?
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
Sorry remind me, what was the original plan? I also look at the Huddersfield layout and don't quite get the logic.

I assume what is now P4 is purely for Manchester stoppers? And the new island platform will handle all slow line trains terminating from Deighton direction.
Originally the lines currently serving platforms 1 & 4 (which will become 2 & 3) were to be the fast lines, meaning the through lines in the station would be paired by use as they will be heading towards Leeds. The current plan is for the new platform 4 (currently 8) to be the Down Fast.
Given they have Transport & Works Act approval, I think that’s highly unlikely.
If the diagram posted above is correct, no changes would be required to switch the use of the two through platforms on the middle island. The current plan means every Down fast service has to cross the throat of platform 3, a conflict that doesn't need to happen if the fast lines are kept to the pair of lines closest to the main building.

Then again, platform use at Huddersfield is a bit puzzling even today. The Leeds stopper nearly always uses bay platform 6 which can only just fit a 185 (and needs a manual override for the ASDO if the accessible space is at the Leeds end), whilst the Bradford service which is almost always a 2-car 158 carrying one man and his dog uses platform 4a.

Why? Given the need for slow trains to cross with fast eastbound trains, doing it in a platform seems a sensible choice. What am I missing?
They only need to cross because of the way the platforms are planned to be used. If the two platforms nearest the main building were the fast lines, no crossing would be necessary.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,404
They only need to cross because of the way the platforms are planned to be used. If the two platforms nearest the main building were the fast lines, no crossing would be necessary.
So how do westbound trains get from the westbound slow line east of Huddersfield to the westbound line without crossing the eastbound line?
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
So how do westbound trains get from the westbound slow line east of Huddersfield to the westbound line without crossing the eastbound line?
A westbound slow train arriving from the east (I think that's what you're getting at) would simply continue into one of the slow line platforms. If going into the new bay, it would have to cross the eastbound slow but wouldn't need to interact with the fast lines at all. If continuing west of Huddersfield the crossing would happen west of the station, but as the layout will (eventually) reduce from 4 tracks to 3 there anyway, some conflicting moves will be unavoidable. The layout as proposed introduces a conflict that doesn't need to be there.

With the layout as proposed, every single slow line arrival into P3 from the Deighton direction will have to cross over the eastbound fast line, and every single fast line departure towards Leeds will have to cross the slow line into platform 3.
East of Huddersfield the slows will be to the north of the formation, so they should use the platforms on that side too. In that case, there would be no interaction between the fasts and slows East of the station in normal operation.
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,094
Location
Lancashire
I assume what is now P4 is purely for Manchester stoppers? And the new island platform will handle all slow line trains terminating from Deighton direction.
Still nothing confirmed, but it's widely anticipated that the Manchester stopper is continuing through Huddersfield and working to York via Castleford.

The only trains terminating at Huddersfield from the West during the day should be the Sheffield services in their own dedicated bay.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,404
A westbound slow train arriving from the east (I think that's what you're getting at) would simply continue into one of the slow line platforms. If going into the new bay, it would have to cross the eastbound slow but wouldn't need to interact with the fast lines at all. If continuing west of Huddersfield the crossing would happen west of the station, but as the layout will (eventually) reduce from 4 tracks to 3 there anyway, some conflicting moves will be unavoidable. The layout as proposed introduces a conflict that doesn't need to be there.

With the layout as proposed, every single slow line arrival into P3 from the Deighton direction will have to cross over the eastbound fast line, and every single fast line departure towards Leeds will have to cross the slow line into platform 3.
East of Huddersfield the slows will be to the north of the formation, so they should use the platforms on that side too. In that case, there would be no interaction between the fasts and slows East of the station in normal operation.
But doing it this way a slow westbound train continuing towards Manchester crosses onto the westbound line in two stages, rather than one if the crossing was west of Huddersfield. So there should be less conflict, not more
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
But doing it this way a slow westbound train continuing towards Manchester crosses onto the westbound line in two stages, rather than one if the crossing was west of Huddersfield. So there should be less conflict, not more
Ah, that does make some sense- two smaller, more manageable conflicts rather than one big one. I was working on the assumption that the plan for the Manchester stopper to run through to Wakefield and beyond was a temporary measure during the upgrade rather than a long-term one. Thus most stoppers would be turning back once the upgrade work was complete.
 

L+Y

Member
Joined
4 Jul 2011
Messages
472
Speaking of Huddersfield, how advanced (if at all?) are the proposals for a third track from Huddersfield to Marsden?
 

stibz

Member
Joined
7 May 2014
Messages
72
Just to marry up to Stibz photos and descriptions here's what I have saved as the final layout.

View attachment 138674
I did see all the plans in pdf, sadly I never downloaded them, can't find them now. But I remember a flyover at Ravensthorpe station mentioned in the plans, looks like that is on the drawing above.
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,032
Location
West Yorkshire / Birmingham
Speaking of Huddersfield, how advanced (if at all?) are the proposals for a third track from Huddersfield to Marsden?
It's certainly something that is being looked at and evaluated given that the TransPennine Route upgrade's scope includes improvements for freight flows, however, it would be too far into the future to know whether it would happen.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
I did see all the plans in pdf, sadly I never downloaded them, can't find them now. But I remember a flyover at Ravensthorpe station mentioned in the plans, looks like that is on the drawing above.
Something I've only just noticed on that plan is the "new" Ravensthorpe station being an island platform. I'm surprised by this as it means the slow lines need to be further apart at that point. Does anyone know the thinking behind this, or should we not be putting much stock in a diagrammatic map which isn't to scale?
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
Ah, that does make some sense- two smaller, more manageable conflicts rather than one big one. I was working on the assumption that the plan for the Manchester stopper to run through to Wakefield and beyond was a temporary measure during the upgrade rather than a long-term one. Thus most stoppers would be turning back once the upgrade work was complete.
If a Manchester stopper turned back in P4, it would need a path across the Down Fast for departure, that coincided with its path on the Up Fast. By turning back in P3, this timetabling constraint/potential conflict is avoided.

To minimise potential conflicts and maximise line capacity, it is best for a turnback siding/platform to be in between the through tracks of a 2-track railway, rather than to one side. That is the principle behind the proposed remodelling of Oxford Road, which would see the current P3 become a west-facing bay to replace the current P5 bay.
 

3RDGEN

Member
Joined
6 Mar 2023
Messages
382
Location
Hull
Ah, that does make some sense- two smaller, more manageable conflicts rather than one big one. I was working on the assumption that the plan for the Manchester stopper to run through to Wakefield and beyond was a temporary measure during the upgrade rather than a long-term one. Thus most stoppers would be turning back once the upgrade work was complete.
If the current service pattern continues there are no conflicting moves on the new layout, the Manc Pic stopper would terminate in the new P3 and depart back tight behind an express to Manchester causing no conflicting moves, as now.

If the plan is to extend the Manc Pic - Huddersfield stopper to Wakefield/York long term or better still relink it to the Hudds - Leeds stopper then you will have a westbound conflict at the east end only. If you have the conflict at the west end then you need to match up having no eastbound trains conflicting with departing tight behind a westbound express which is harder to achieve. As mentioned above doing the crossover in two steps is easier to plan, the stopper can be timed to sit in Hudds P3 to allow for this.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
I did see all the plans in pdf, sadly I never downloaded them, can't find them now. But I remember a flyover at Ravensthorpe station mentioned in the plans, looks like that is on the drawing above.
As far as I can see, all the plans and documents for the Transport and Works Act application are still online. I just searched for "Huddersfield Westtown" and found this:

 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,526
Location
Yorkshire
If the current service pattern continues there are no conflicting moves on the new layout, the Manc Pic stopper would terminate in the new P3 and depart back tight behind an express to Manchester causing no conflicting moves, as now.

If the plan is to extend the Manc Pic - Huddersfield stopper to Wakefield/York long term or better still relink it to the Hudds - Leeds stopper then you will have a westbound conflict at the east end only. If you have the conflict at the west end then you need to match up having no eastbound trains conflicting with departing tight behind a westbound express which is harder to achieve. As mentioned above doing the crossover in two steps is easier to plan, the stopper can be timed to sit in Hudds P3 to allow for this.
Yeah, I can see the error in my thinking now- I don't travel West of Huddersfield much, so didn't consider the implications at that end of the station, not least because the third track is still further from happening than the changes in the north/easterly direction.

I'd be wary of running the Leeds stopper through to Manchester though, as that prevents it being an EMU until the wires go up over the hills. It also didn't work particularly well back in 2018, though that was on the existing layout with less opportunities for overtaking.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
Something I've only just noticed on that plan is the "new" Ravensthorpe station being an island platform. I'm surprised by this as it means the slow lines need to be further apart at that point. Does anyone know the thinking behind this, or should we not be putting much stock in a diagrammatic map which isn't to scale?
I would imagine the land take in the area is determined by the need for a smooth alignment for the fast lines, together with the fact that the existing/slow lines have a wiggle to the north. There are much larger scale maps still online at the link I posted above.
 