Hi All,
Now the Easter work is over, can anyone advise what's left to do platform wise & the timescales involved?
thanks,
Hi All,
Now the Easter work is over, can anyone advise what's left to do platform wise & the timescales involved?
Finish off P11 as a through platform, lay track and open as up main loop. Happening between now and the August BH weekend.
Close P10 when P11 re-opens, re-lay track to final position and then rebuild the platform edge out to its final position, at higher level to correspond to P11 section already built. I reckon about 6 months work from August BH weekend, although it was earlier suggested it would take much longer.
Close P7 to rebuild it out to be a couple of metres wider. Roughly where the up main through line was, but not exactly. Starts in autumn some time, up to about 6 months work. Includes resurfacing of currently out of use P3.
Resurface P8 and P9, renew copings etc, extend P8 at west end to match P9. This will be done in sections, with 5 car train length limit at certain times. Not sure of current dates.
Complete London end canopies, and platform building work on all of platforms 8-11. Add platform canopy to P7, and final section of main roof up to the transfer deck to align with newly widened platform. (That's the reason for the white plastic sheeted side of the new southern stairs/escalator area - it's still only 3/4 the width of the final building.)
Upgrade surfaces/copings of platforms 1 and 2, and fit their new canopies. Should be possible to do this without a long closure - as was done with the 'southern' platforms, the old 4A/4B. (I'm told the foundations for their canopies are being progressed already, under those temporary boards on the platform surface.
Build new canopy over the open area in vicinity of P4, 5 & 6 where old lift, stairs and escalators will be removed.
All to be complete by Easter 2014, supposedly.
However the latest edition of NR's 'Reading Station News' leaflet does say that all station work will be finished February 2014 - how this works out if P10 is supposedly not finishing until Dec 2014 I leave open to question...
Discussed in previous post - 'All track-work except platforms 1 & 2 replaced'Finish off P11 as a through platform, lay track and open as up main loop. Happening between now and the August BH weekend.
Close P10 when P11 re-opens, re-lay track to final position and then rebuild the platform edge out to its final position, at higher level to correspond to P11 section already built. I reckon about 6 months work from August BH weekend, although it was earlier suggested it would take much longer.
Close P7 to rebuild it out to be a couple of metres wider. Roughly where the up main through line was, but not exactly. Starts in autumn some time, up to about 6 months work. Includes resurfacing of currently out of use P3.
Resurface P8 and P9, renew copings etc, extend P8 at west end to match P9. This will be done in sections, with 5 car train length limit at certain times. Not sure of current dates.
Complete London end canopies, and platform building work on all of platforms 8-11. Add platform canopy to P7, and final section of main roof up to the transfer deck to align with newly widened platform. (That's the reason for the white plastic sheeted side of the new southern stairs/escalator area - it's still only 3/4 the width of the final building.)
Upgrade surfaces/copings of platforms 1 and 2, and fit their new canopies. Should be possible to do this without a long closure - as was done with the 'southern' platforms, the old 4A/4B. (I'm told the foundations for their canopies are being progressed already, under those temporary boards on the platform surface.
Build new canopy over the open area in vicinity of P4, 5 & 6 where old lift, stairs and escalators will be removed.
All to be complete by Easter 2014, supposedly.
However the latest edition of NR's 'Reading Station News' leaflet does say that all station work will be finished February 2014 - how this works out if P10 is supposedly not finishing until Dec 2014 I leave open to question...
I noticed today, the stanchions for the OLE have started to appear on the west curve at the Reading West Jn end.
A sign has now gone up in the public underpass preventing cycling. As I predicted the tunnel is not quite wide enough for two cycle lanes and pedestrians to manage. A real shame they did not build a tunnel wide enough for both.
I think it's more down to cyclists bombing it down the slopes either side and turning into a 90 degree blind corner without seeing or thinking about pedestrians (depending on type of cyclist...)
... A real shame they did not build a tunnel wide enough for both.
I think it's clear that no consideration was given to cycle infrastructure or they would not have put in a 90 degree blind bend corner because of the obvious consequences you mention.
They didn't actually build a 'new tunnel' though - they mostly just overhauled the existing subway, except for the furthest north section where it widens out. They increased its usable width by about 50% compared to the old setup, which had a partition wall down the centre, but they retained about 25% on the west side which was reserved for station electrical and mechanical services.
--- old post above --- --- new post below ---
The blind corners are not permanent. The north entrance will be approached directly from the Vastern Rd direction, and the south entrance will eventually lead out into a large open space (where the demolition work is paused until the portakabins are removed).
As has been mentioned above, the subway was only refurbished and the 90 degree turn is temporary. The costs of making the subway larger would have been huge (assuming it's possible) - specially when the Vastern Road bridge (now) has designated cycle/bus lanes.I think it's clear that no consideration was given to cycle infrastructure
Cow lane bridges will have cycle lanes (though one of the old ones still needs removing - I believe scheduled for the May bank holiday)
I have a few questions on the track changes as a result of my first trip in a couple of years through the station. Could not see the answers elsewhere in the time I had to look.
1. There seems to be a blanket speed restriction over the whole station. Is this going to remain until work progresses further? I expected to run into the station a little faster on the down main to Bristol, although there is obviously a lot more work to do.
2. Are the up and down Bristol lines aligned correctly through the station and on the approaches? I could not tell when on the down main and on the up main we got diverted into platform 15. The down main obviously needs realignment near Tilehurst where it swings sharply to join the old alignment. When is this planned?
3. What are the intended speeds on the Bristol main lines through the station? I suppose as nearly all trains stop at Reading high speed through the station is not so important. Will trains be able to run at speed up to the main line platforms and just do a routine service brake to enter the platforms or will there be a mile or more of slowish running due to the alignment?
Finally full marks to all involved. It is a massive project to do and keep trains running.
This image on the link shows is a diagram of the track through Reading station once the work is completed:
http://richardwillisuk.files.wordpress.com/2009/05/stn-phases1.jpg
It shows that the speed limit through platforms 8-11 is planned to be 50mph although through platforms 9-10 100mph 'is achievable subject to future signalling improvements'.
In my memory the speeds on the main lines have never been more than 80. It is correct that the relief lines used to be 75, but realignment of the main lines mean this is no longer possible.If these are the final speeds, they do not even match those before the changes.
The Reliefs had a 75mph limit through the station (old p8/9, new p9/10) until recently (mainly used by through freight trains) .
This image on the link shows is a diagram of the track through Reading station once the work is completed:
http://richardwillisuk.files.wordpress.com/2009/05/stn-phases1.jpg
It shows that the speed limit through platforms 8-11 is planned to be 50mph although through platforms 9-10 100mph 'is achievable subject to future signalling improvements'.
2. Are the up and down Bristol lines aligned correctly through the station and on the approaches? I could not tell when on the down main and on the up main we got diverted into platform 15. The down main obviously needs realignment near Tilehurst where it swings sharply to join the old alignment. When is this planned?
Since the station re-opened and four new platforms opened after the Easter break, furious commuters have been complaining they cannot get on to Platform 10 for the fast trains to London.
Ongoing works to the platform means it does not have the capacity for the crowds and people are being held at the top of the escalators.
Mr Wilson said: “If they knew the main through platform to London had work still going on while others had been completed, surely the sensible thing to do was to route the trains to the platforms which could take the most people rather than hold commuters at the top of the escalators.
“Commuters aren’t very happy with First Great Western.”
He said matters were not helped by the lack of helpfulness of the FGW staff.
Mr Wilson said: “There are basic customer service things that First Great Western is not getting right and to be honest they haven’t got them right for a long time. My impression is they are not investing enough in staff training and staff support.”
Network Rail worked over the Easter period to open new platforms and install the huge new pedestrian bridge with escalators to each platform as part of the multi-million pound improvements to the rail network around Reading.
Mr Wilson said: “It’s not a good advert for a new station where we have invested £850 million if this sort of thing is going on.”
James Davis, a spokesman for FGW said yesterday: “The width of Platform 10 at Reading Station has been restricted while work to bring more platforms into use continue.
“To help ease congestion at peak times we have been asking customers getting on trains from Platform 10 to wait on the passenger bridge to allow customers to get off the train safely before boarding the train themselves.
“Work to widen access on to the platform to avoid this situation started last week.
“It was completed over the weekend and was open to passengers from this morning.”
Reasonable points and it certainly has been crowded (not sure how much wider it is now, I didn't even notice that it had changed!). My question is whether there was an alternative to this situation - i.e. could an alternative pair of platforms have been used for the up main until P11 was completed? Also to what extent are FGW responsible - I would have they wouldn't have had much say over the order of building works?
There's complaint in the local press about the state of platform 10:
Reasonable points and it certainly has been crowded (not sure how much wider it is now, I didn't even notice that it had changed!). My question is whether there was an alternative to this situation - i.e. could an alternative pair of platforms have been used for the up main until P11 was completed? Also to what extent are FGW responsible - I would have they wouldn't have had much say over the order of building works?