Ta! Any vehicle numbers quoted?
It's entirely possible that the second unit was delayed by efforts to get the classic sets ready in time for the December timetable change and then the effects of the holiday period. If that's the case, we might be able to expect one unit a week from here on, as per the original schedule.
Can confirm refurb number 3 Won't be leaving today can only assume the path in place for today was backup incase it didn't leave the other day. Also the refurb set won't be seen in Inverness untill the back sidings work is complete.
Can confirm refurb number 3 Won't be leaving today can only assume the path in place for today was backup incase it didn't leave the other day.
The path would have auto activated 2hrs before booked departure.Checked RTT and the path was activated earlier today. I’m assuming this is an automatic action if it’s not set #3 heading north?
What difference does classic vs refurbed HST make as far as the sidings are concerned?Can confirm refurb number 3 Won't be leaving today can only assume the path in place for today was backup incase it didn't leave the other day. Also the refurb set won't be seen in Inverness untill the back sidings work is complete.
At a guess, the work is possibly to install waste tank emptying facilities?What difference does classic vs refurbed HST make as far as the sidings are concerned?
Ah yes. That would make sense.At a guess, the work is possibly to install waste tank emptying facilities?
This brings about the question: what if the refurbished trains were delivered on time? The original schedule stated that refurbished sets would have been working Inverness services months ago. Or has this work been intentionally delayed?Also the refurb set won't be seen in Inverness untill the back sidings work is complete.
I would expect it tbh.That's what I thought too - I wonder if Inverness train crews will be having day trips to Perth for training?
Also a very valid point currently the classics have to have at least 1 engine running overnight as they have no battery hookup in the sidings. Until these works are done the refurbs won't be seen does begger the question that the works should have been done quickerThis brings about the question: what if the refurbished trains were delivered on time? The original schedule stated that refurbished sets would have been working Inverness services months ago. Or has this work been intentionally delayed?
At a guess, the work is possibly to install waste tank emptying facilities?
WHY is this work only happening now? It's been known since 2015 that the HSTs were coming so there's been plenty of time to get that sort of work done.
What putting CET equipment in the sidings at Inverness? Of course that could've been done.They were working and fully employed by GWR so nothing could be done until off lease and transferred to Scotrail
He's referring to the servicing facilities and not the trains themselves.They were working and fully employed by GWR so nothing could be done until off lease and transferred to Scotrail
In answer to your question, 41137, 42502, 42265, 41116, 42257, 42578, 42350 and 42259 were the vehicles being moved.Ta! Any vehicle numbers quoted?
Ta very much - appreciated.In answer to your question, 41137, 42502, 42265, 41116, 42257, 42578, 42350 and 42259 were the vehicles being moved.
They were working and fully employed by GWR so nothing could be done until off lease and transferred to Scotrail
It's this sort of glimpse that makes you ever more suspicious about basic incompetence in management of the project. Trains not converted, staff not trained, servicing facilities not installed, terrible communication about the consequences of the delays, it goes on and on...WHY is this work only happening now? It's been known since 2015 that the HSTs were coming so there's been plenty of time to get that sort of work done.
I was referring to the stabling/servicing infrastructure...not the trains themselves.
What difference does classic vs refurbed HST make as far as the sidings are concerned?
Would it actually be possible to run all the diagrammed HST services to/from Inverness (classic or refurb) at the moment then? As in, would the lack of stabling space be the constraint even if enough drivers/crews were trained and there were enough HSTs to go round?There are 3 sidings out the back of Inverness CMD - 1 has been extended, but the other 2 haven't been relaid yet. There is physically no room for another HST, be it a Classic or a Refurb.
Basically, the issue is that there is no space to store a driver training train & a refurb training train as well
At a guess, the work is possibly to install waste tank emptying facilities?
Would it actually be possible to run all the diagrammed HST services to/from Inverness (classic or refurb) at the moment then? As in, would the lack of stabling space be the constraint even if enough drivers/crews were trained and there were enough HSTs to go round?
What putting CET equipment in the sidings at Inverness? Of course that could've been done.
Are the HSTs being left with one power car running all the time then ? At all depots or only some? As I understand it from posts elsewhere, cold starts seriously affect the service life of the engines, hence they need preheated either from a shore supply or from the power car at the other endWhat SHOULD have been done was the installation of shore supplies - would have saved a fortune in fuel bills!
They're certainly being shut down when they're parked at Dundee.Are the HSTs being left with one power car running all the time then ? At all depots or only some?
As the IET's were so late and kept failing and no one could fix them and wires took so long because of H & S is a good excuse. (My excuse to have a rant).They were working and fully employed by GWR so nothing could be done until off lease and transferred to Scotrail